The purpose of the project is to bring a reliable livestock watering source to the Gilmore Allotment on the Buffalo Gap National Grassland by installing 2 buried water lines and 2 water tanks.
Location
Approximately 2 miles Southeast of Farmingdale, SD.
Project timeline
1
Scoping Start
04/03/2025
2
Decision
05/2025 (Estimated)
3
Implementation
07/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (9), 36 Cfr 220.6(E)(9) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Grazing Allotment Management |
| Gilmore Water Line | Decision Signed Date: 05/27/2025 |
| Forests | Nebraska National Forest |
| Districts | Fall River Ranger District |
| Legal Land Description | Not Applicable |