Nebraska National Forests and Grasslands — Project Detail

25 projects with crawled detail · milestones · contacts · documents

Nebraska National Forests and Grasslands

R02 Rocky Mountain · 25 projects · crawled 2026-06-17
In Progress 2 Developing Proposal 7 On Hold 1 Completed 15
Decision Memo 13 Categorical Exclusion 8 Environmental Assessment 3 Environmental Impact Statement 1
16 with documents 13 with comments page
Categorical Exclusion · Fall River Ranger District · updated 5/27/2026 · decision 7/2026 (Estimated)
Fall River West Geographic Area · Fall River, South Dakota

Install a reliable water distribution system in West Association West Pasture.

Grazing management
NEPA Start Date
1/8/2026
Finding/Decision Date
MATT LUCAS · matt.lucas@usda.gov
NEPA / regulatory detail
Categorical ExclusionUSDA-33d-USFS
Bovee Wildfire Reforestation Developing Proposal
Categorical Exclusion · Bessey Ranger District · updated 5/13/2026 · decision 8/2026 (Estimated)
Nebraska National Forest south of Halsey, NE · Thomas, Nebraska

Reforestation within and around the area of the Nebraska National Forest affected by the 2022 Bovee Wildfire.

Vegetation management (other than forest products)
NEPA Start Date
2/10/2026
Finding/Decision Date
Sarah Myers · sarah.myers2@usda.gov
NEPA / regulatory detail
Categorical ExclusionUSDA-47d-USFS
Sheriff West Riparian Fencing Developing Proposal
Categorical Exclusion · Ft. Pierre Ranger District · updated 5/5/2026 · decision 5/2026 (Estimated)
Sheriff West Pasture - FPNG · Jones, South Dakota

Installation of an approximately 0.25 mile riparian buffer fence to protect resources along the unnamed tributary to the East Branch War Creek and better manage livestock grazing and distribution.

Vegetation management (other than forest products)
NEPA Start Date
11/25/2025
Finding/Decision Date
Kelly Waage · kelly.waage@usda.gov
NEPA / regulatory detail
Categorical ExclusionUSDA-33d-USFS
Categorical Exclusion · Ft. Pierre Ranger District · updated 4/28/2026 · decision 7/2026 (Estimated)
East & Northeast Engen Pastures - FPNG · Lyman, South Dakota

Removal of approximately 3,775 feet of fence around the western and southern border of the Engen Northeast Pasture to consolidate the pasture into one with Engen East. The intention is to remove livestock watering pressure from the wetland area in and around Cottonwood Dam. Cottonwood Dam is a popul

Grazing management
NEPA Start Date
1/6/2026
Finding/Decision Date
Kelly Waage · kelly.waage@usda.gov
NEPA / regulatory detail
Categorical ExclusionUSDA-33d-USFS
Decision Memo · Wall Ranger District · updated 4/27/2026
Approximately 4 miles southeast of Wall, SD. · Pennington, South Dakota

Rebuild the existing three phase powerline along the current route.

Special use management
Scoping Start
08/21/2025
Decision
03/2026 (Estimated)
Implementation
04/2026 (Estimated)
Project documents
Ericka Lans · ericka.lans@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (2), 36 Cfr 220.6(E)(2)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
ForestsNebraska National Forest
DistrictsWall Ranger District
Legal Land DescriptionNot Applicable
American Creek North Fence Developing Proposal
Categorical Exclusion · Ft. Pierre Ranger District · updated 4/9/2026 · decision 7/2026 (Estimated)
American Creek North Pasture - FPNG · Lyman, South Dakota

Convert the existing temporary fence, that has been in place for over 25 years, to a permanent fence. This would permanently split the American Creek North Pasture into two pastures, American Creek Northwest and American Creek Northeast.

Grazing management
NEPA Start Date
1/6/2026
Finding/Decision Date
Kelly Waage · kelly.waage@usda.gov
NEPA / regulatory detail
Categorical ExclusionUSDA-33d-USFS
Decision Memo · Pine Ridge Ranger District · updated 2/23/2026
Nebraska National Forest south of Chadron, NE · Dawes, Nebraska

Conduct prescribed burns on two different units, about 1,100 acres total, to reduce heavy fuel loading.

Vegetation management (other than forest products)Fuels management
Scoping Start
02/28/2025
Decision
02/2026 (Estimated)
Implementation
03/2026 (Estimated)
Project documents
Benjamin Jech · benjamin.j.jech@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (6), 36 Cfr 220.6(E)(6)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityFuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements
ForestsNebraska National Forest
DistrictsPine Ridge Ranger District
Legal Land DescriptionNot Applicable
Categorical Exclusion · Ft. Pierre Ranger District · updated 1/22/2026 · decision 7/2026 (Estimated)
Sletto North Winter Pasture of the Fort Pierre National Grassland · Jones, South Dakota

Install a reliable water distribution system in the Sletto North Winter Pasture of the Fort Pierre National Grassland by extending a previously approved water line from the adjacent Sheriff East Pasture.

Grazing management
NEPA Start Date
1/14/2026
Finding/Decision Date
Kelly Waage · kelly.waage@usda.gov
NEPA / regulatory detail
Categorical ExclusionUSDA-33d-USFS
Dry Hole #3 Water Line and Tank Developing Proposal
Categorical Exclusion · Ft. Pierre Ranger District · updated 1/7/2026 · decision 7/2026 (Estimated)
Cut Off Summer & Dry Hole #3 Pastures - FPNG · Lyman, South Dakota

Install a reliable water distribution system in the Dry Hole #3 Pasture by extending an existing water line from the adjacent Cut Off Summer Pasture. The water supply would originate from an existing water tank location in the Cut Off Summer Pasture and run east into the Dry Hole #3 Pasture.

Grazing management
NEPA Start Date
1/6/2026
Finding/Decision Date
Kelly Waage · kelly.waage@usda.gov
NEPA / regulatory detail
Categorical ExclusionUSDA-33d-USFS
SDDOT Igloo Access Road SUP Developing Proposal
Categorical Exclusion · Fall River Ranger District · updated 1/7/2026 · decision 7/2026 (Estimated)
Approximately 1 mile east of Igloo, SD · Fall River, South Dakota

The proposed action includes the issuance of a special use permit to the SD Department of Transportation for the authorized construction of an access road to the community of Igloo, SD. The road would bisect approximately 630 feet of USFS System Lands.

Special use management
NEPA Start Date
1/6/2026
Finding/Decision Date
Ericka Lans · ericka.lans@usda.gov
NEPA / regulatory detail
Categorical ExclusionUSDA-28d-USFS
Decision Memo · Nebraska National Forest All Units · updated 11/25/2025
Approximately 5 miles southwest of Creston, SD. · Pennington, South Dakota

Install a reliable livestock watering distribution system in the Circle C and Cole Draw Allotments of the Buffalo Gap National Grassland.

Grazing management
Scoping Start
07/22/2025
Decision
11/2025 (Estimated)
Implementation
06/2026 (Estimated)
Project documents
Matthew Lucas · matthew.lucas@usda.gov
NEPA / regulatory detail
Categorical ExclusionFsa 7 Cfr 779.32 E(2)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityGrazing Allotment Management
ForestsNebraska National Forest
DistrictsFall River Ranger District
Legal Land DescriptionNot Applicable
Environmental Assessment · Wall Ranger District · updated 11/21/2025
Approximately 4.25 miles southwest of the town of Scenic, South Dakota. · Pennington, South Dakota

Build about 1.3 miles of allotment division fence.

Grazing management
Scoping Start
11/21/2024
Comment Period
11/21/2024
Objection Period Start
08/23/2025
Decision
11/2025 (Estimated)
Implementation
04/2026 (Estimated)
Project documents
Jacob Rohrer · Jacob.Rohrer@usda.gov
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityGrazing Allotment Management; Grazing Structural Improvements
ForestsNebraska National Forest
DistrictsWall Ranger District
Legal Land DescriptionT3S, R12E, Sections 23 and 26
Decision Memo · Fall River Ranger District · updated 10/1/2025
Approximately 4 miles west of Ardmore, SD. · Fall River, South Dakota

Install a reliable water distribution system in 5 pastures of the Furrow Allotment that includes 7.27 miles of water line and 13 water tanks.

Grazing management
Scoping Start
08/27/2025
Decision
09/2025 (Estimated)
Implementation
04/2026 (Estimated)
Project documents
Matthew Lucas · matthew.lucas@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (9), 36 Cfr 220.6(E)(9)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityGrazing Allotment Management; Grazing Structural Improvements
ForestsNebraska National Forest
DistrictsFall River Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Nebraska National Forest All Units · updated 9/24/2025
Approximately 1 mile west of Red Shirt, SD. · Custer, South Dakota

The Pasture 7 Access Special Use Permit Project proposes to permit access to private lands on an existing administrative road.

Special use management
Scoping Start
07/21/2025
Decision
09/2025 (Estimated)
Implementation
10/2025 (Estimated)
Project documents
Matthew Lucas · matthew.lucas@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
ForestsNebraska National Forest
DistrictsFall River Ranger District
Legal Land DescriptionT4S, R10E, 07
Decision Memo · Bessey Ranger District · updated 9/5/2025
Approximately 1 mile west of Halsey, NE. · Thomas, Nebraska

Reroute of overhead powerline due to replacement of bridge structure over the Middle Loupe River near Halsey, NE.

Special use management
Scoping Start
08/29/2025
Decision
09/2025 (Estimated)
Implementation
05/2026 (Estimated)
Project documents
Ericka Lans · ericka.lans@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
ForestsNebraska National Forest
DistrictsBessey Ranger District
Legal Land DescriptionSec. 2 SW 1/4, Sec. 3 SEl/4, S\.\1 1/4, Sec. 4, SEl/4SE1/4, Sec. 9, 1E1/4, NWl/4SEl/4, SWl/4
Decision Memo · Bessey Ranger District · updated 8/18/2025
NE HWY 86B over the Middle Loup River near Halsey, NE. · Thomas, Nebraska

Nebraska Department of Transportation bridge replacement on NE HWY 86B over the Middle Loup River.

Special use managementRoad management
Scoping Start
07/24/2025
Decision
08/2025 (Estimated)
Implementation
03/2026 (Estimated)
Ericka Lans · ericka.lans@usda.gov
NEPA / regulatory detail
Categorical Exclusion40 Cfr 1506.3(D)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations; Road Maintenance
ForestsNebraska National Forest
DistrictsBessey Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Fall River Ranger District · updated 7/28/2025
Approximately 11 miles west of Edgemont, SD. · Fall River, South Dakota

To improve livestock grazing distribution the installation of 4 water tanks and 2.09 miles of water line in the South Pasture and 3 water tanks and 1.53 miles of water line in the North Pasture of the Simon Allotment.

Grazing management
Scoping Start
05/15/2025
Decision
07/2025 (Estimated)
Implementation
09/2025 (Estimated)
Project documents
Matthew Lucas · matthew.lucas@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (9), 36 Cfr 220.6(E)(9)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityGrazing Structural Improvements
ForestsNebraska National Forest
DistrictsFall River Ranger District
Legal Land DescriptionT9S R1E Section 6 and 32 T10S R1E Section 7
Environmental Assessment · Fort Pierre Ranger District · updated 7/7/2025
Approximately 15 miles southwest of Fort Pierre, SD on the Fort Pierre National Grassland. · Jones; Stanley, South Dakota

Authorize the installation of approximately 10 miles of buried waterline as well as 14 water tanks and 6 water lots.

Grazing managementVegetation management (other than forest products)
Scoping Start
05/29/2024
Comment Period
03/20/2025
Objection Period Start
05/27/2025
Decision
07/2025 (Estimated)
Implementation
09/2025 (Estimated)
Project documents
Kelly Waage · kelly.waage@usda.gov
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityGrazing Allotment Management; Rangeland Vegetation Improvements; Grazing Structural Improvements
ForestsNebraska National Forest
DistrictsFort Pierre Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Wall Ranger District · updated 6/25/2025
Approximately 20 miles Southwest of Wall, SD · Pennington, South Dakota

Improvement of rangeland infrastructure and water sources for the use of livestock grazing as a vegetation management tool in the Imlay West Pasture of the Buffalo Gap National Grassland.

Grazing management
Scoping Start
04/21/2025
Comment Period
04/21/2025
Decision
06/2025 (Estimated)
Implementation
09/2025 (Estimated)
Project documents
Jacob Rohrer · Jacob.Rohrer@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.12 (4), 36 Cfr 220.6(D)(4); Fsa 7 Cfr 779.32 E(2)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityGrazing Structural Improvements
ForestsNebraska National Forest
DistrictsWall Ranger District
Legal Land DescriptionT 4S R13E Sec. 11, 14, and 23
Decision Memo · Fort Pierre Ranger District · updated 6/16/2025
Throughout the Fort Pierre National Grassland. · Lyman; Stanley, South Dakota

Special use authorization for the installation of 28.77 miles of fiber optic cable in existing road rights-of-way adjacent to USFS System lands.

Special use management
Scoping Start
03/13/2024
Decision
06/2025 (Estimated)
Implementation
07/2025 (Estimated)
Project documents
NEPA / regulatory detail
Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
ForestsNebraska National Forest
DistrictsFort Pierre Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Fall River Ranger District · updated 6/10/2025
Approximately 0.25 miles northwest of French Creek Campground on the Buffalo Gap National Grassland. · Custer, South Dakota

Installation of structural guides or boundaries to designate two parking areas along a US Forest Service road.

Recreation management
Scoping Start
05/15/2025
Decision
06/2025 (Estimated)
Implementation
09/2025 (Estimated)
Project documents
Matthew Lucas · matthew.lucas@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (22), 36 Cfr 220.6(E)(22)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityTravel Management
ForestsNebraska National Forest
DistrictsFall River Ranger District
Legal Land DescriptionNot Applicable
Gilmore Water Line Completed
Decision Memo · Fall River Ranger District · updated 5/28/2025
Approximately 2 miles Southeast of Farmingdale, SD. · Pennington, South Dakota

The purpose of the project is to bring a reliable livestock watering source to the Gilmore Allotment on the Buffalo Gap National Grassland by installing 2 buried water lines and 2 water tanks.

Grazing managementVegetation management (other than forest products)
Scoping Start
04/03/2025
Decision
05/2025 (Estimated)
Implementation
07/2025 (Estimated)
Project documents
Mandy Irwin · Mandy.Irwin@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (9), 36 Cfr 220.6(E)(9)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityGrazing Allotment Management
ForestsNebraska National Forest
DistrictsFall River Ranger District
Legal Land DescriptionNot Applicable
Environmental Assessment · Fort Pierre Ranger District · updated 5/5/2025
Approximately 20 miles south of Fort Pierre, SD. · Lyman, South Dakota

Permit for the South Dakota Department of Transportation to construct a snow fence on USFS System Lands adjacent to US Highway 83.

Special use management
Scoping Start
05/21/2024
Comment Period
12/26/2024
Objection Period Start
03/20/2025
Decision
05/2025 (Estimated)
Implementation
06/2025 (Estimated)
Project documents
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivitySpecial Use Authorizations
ForestsNebraska National Forest
DistrictsFort Pierre Ranger District
Legal Land DescriptionSection 29, T107N, R79W
Environmental Impact Statement · Nebraska National Forest All Units · updated 12/5/2024
Nebraska National Forests and Grasslands · Blaine; Cherry; Dawes; Sioux; Thomas; Custer; Fall River; Jackson; Jones; Lyman; Pennington; Stanley, Nebraska; South Dakota

The Nebraska National Forests and Grasslands propose to update the Forests' guidance for plant management strategies through an environmental analysis for the management of invasive, noxious, alien, non-native, and undesirable native plant species.

Vegetation management (other than forest products)
NOI in Federal Register
01/10/2023
DEIS NOA in Federal Register
03/22/2024
FEIS NOA in Federal Register
08/16/2024
Objection Period Start
08/09/2024
Decision
12/2024 (Estimated)
Implementation
12/2024 (Estimated)
Project documents
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityForest Vegetation Improvements; Noxious Weed Treatments; Rangeland Vegetation Improvements
ForestsNebraska National Forest
DistrictsNebraska National Forest All Units
Legal Land DescriptionNot Applicable
Decision Memo · Fall River Ranger District · updated 12/19/2023
Approximately 5 miles southeast of Oelrichs, SD · Fall River, South Dakota

Installation of a new fence to protect the dam face, part of the waterbody and spring source from livestock affects while providing a source of water for livestock and enhancing recreational opportunities for the public.

Recreation managementWildlife, fish, rare plantsVegetation management (other than forest products)Watershed management
Scoping Start
12/2023 (Estimated)
Decision
01/2024 (Estimated)
Implementation
04/2024 (Estimated)
Project documents
Matthew Lucas · matthew.lucas@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (6), 36 Cfr 220.6(E)(6)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecies Habitat Improvements; Rangeland Vegetation Improvements; Watershed Improvements
ForestsNebraska National Forest
DistrictsFall River Ranger District
Legal Land DescriptionNot Applicable