Authorize the installation of approximately 10 miles of buried waterline as well as 14 water tanks and 6 water lots.
Location
Approximately 15 miles southwest of Fort Pierre, SD on the Fort Pierre National Grassland.
Project timeline
1
Scoping Start
05/29/2024
2
Comment Period
03/20/2025
3
Objection Period Start
05/27/2025
4
Decision
07/2025 (Estimated)
5
Implementation
09/2025 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Grazing Allotment Management; Rangeland Vegetation Improvements; Grazing Structural Improvements |
| War Creek Waterline Project | Decision Signed Date: 07/07/2025 |
| Forests | Nebraska National Forest |
| Districts | Fort Pierre Ranger District |
| Legal Land Description | Not Applicable |