Environmental Assessment Completed

Burnt Creek LLC Access

Rio Grande National Forest Rio Grande, Colorado Rio Grande National Forest All Units

Authorize a permit for occupancy and use for the purpose and constructing and maintaining a driveway to access private land. The project occurs in designated Colorado Roadless.

Location

North of Jasper, Colorado. South of Blowout Pass Special Interest Area.

Project timeline

1
Scoping Start
04/02/2025
2
Comment Period
04/09/2025
3
Objection Period Start
07/09/2025
4
Decision
09/2025 (Estimated)
5
Implementation
10/2025 (Estimated)

NEPA / regulatory detail

Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityRoadless Area Management
Burnt Creek LLC AccessDecision Signed Date: 09/04/2025
ForestsRio Grande National Forest
DistrictsConejos Peak Ranger District
Legal Land DescriptionT.37N.,R.5E., Section 20 and 29 NMPM
Regulations, directives, ordersSpecial area management