Decision Memo Completed

Special Uses - Empire Electric Dolores River Overhead

San Juan National Forest Montezuma, Colorado Mancos/Dolores Ranger District

Empire Electric Association has an existing, buried electrical line crossing the Dolores River that is at risk of washing out due to erosion. They propose to construct a replacement overhead line, which will require installation of 2 wood poles.

Location

Just south of highway 145, approximately 1 mile west of Stoner

Project timeline

1
Scoping Start
03/03/2025
2
Decision
06/2025 (Estimated)
3
Implementation
06/2025 (Estimated)

NEPA / regulatory detail

Categorical ExclusionNtia_C(8)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityElectric Transmission; Special Use Authorizations
Decision Memo - Empire Electric Dolores River Overhead ProjectDecision Signed Date: 06/11/2025
ForestsSan Juan National Forest
DistrictsMancos/Dolores Ranger District
Legal Land DescriptionNot Applicable
Special use management