Breckenridge Ski Resort (BSR) is proposing projects on Peak 9 including the installation of a new gondola teaching terrain, and the replacement of C-Chair to relieve portal crowding and improve the experience for guests learning to ski and ride.
Location
The improvements will be located on Peak 9, within the Breckenridge Ski Resort special use permit area and operational boundary.
Project timeline
1
Scoping Start
05/14/2024
2
Comment Period
05/14/2024
3
Decision
06/2025 (Estimated)
4
Implementation
07/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (22), 36 Cfr 220.6(E)(22) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Breckenridge Peak 9 Projects 2024 | Decision Signed Date: 06/10/2025 |
| Forests | White River National Forest |
| Districts | East Zone/Dillon Ranger District |
| Legal Land Description | Not Applicable |