Decision Memo Completed

Pad 31 to Pad 42 Pipeline Project

Carson National Forest Rio Arriba, New Mexico Jicarilla Ranger District

Harvest Four Corners, LLC (Harvest) and LOGOS Operating, LLC (LOGOS) propose to construct and operate respective pipelines and associated facilities within an existing pipeline corridor. Also, LOGOS proposes to drill two natural gas wells.

Location

Laguna Seca Mesa

Project timeline

1
Scoping Start
03/13/2025
2
Decision
04/2025 (Estimated)
3
Implementation
04/2025 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.3 (3)
Special AuthorityOil & Gas - Sec. 390, Energy Policy Act Of 2005 (Sec 390)
Notice and Comment RegulationNot Subject to Regulations
Project ActivityNatural Gas
Decision Decided Date04/24/2025
ForestsCarson National Forest
DistrictsJicarilla Ranger District
Legal Land DescriptionNew Mexico Principal Meridian T. 31 N., R 5 W. sec. 32, 33, 34, 35, and 36.
Minerals and geology