Decision Memo Completed

Telecommunications Site Improvements

Cibola National Forest and National Grasslands Cibola, New Mexico Mount Taylor Ranger District

Burlington Northern Santa Fe Railway Co. proposes to install a concrete slab and replace their communication building on La Mosca Peak. El Paso Natural Gas Co. proposes to install a concrete slab and replace their generator on Microwave Ridge.

Location

14 & 12 miles northeast of Grants, NM

Project timeline

1
Scoping Start
03/03/2016
2
Decision
03/2016 (Estimated)
3
Implementation
06/2016 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations; Research And Development
Burlington Northern Santa Fe Railway Co.Telecommunications Site ImprovementDecision Signed Date: 03/28/2016
ForestsCibola National Forest
DistrictsMount Taylor Ranger District
Legal Land DescriptionNot Applicable
Special use management