Reissue special use authorization for an existing natural gas pipeline. Removed from PALS - no DM required.
Location
Crosses BKNG units 46, 54, & 63
Project timeline
1
Scoping Start
10/01/2018
2
Decision
02/2022 (Estimated)
3
Implementation
03/2022 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (11), 36 Cfr 220.6(D)(11) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Cibola National Forest |
| Districts | Black Kettle National Grassland |
| Legal Land Description | Not Applicable |