Proposal to install (1) 4' x 10' concrete pad with 500-gallon propane tank, (1) 5' x 9' concrete pad with propane generator, 15' of sub-surface gas line, and 90' of sub-surface electrical conduit within the existing Datil Communication Site boundary.
Location
Proposed action would fall within the existing Datil Communication Site, Datil, New Mexico
Project timeline
1
Scoping Start
12/06/2024
2
Decision
02/2025 (Estimated)
3
Implementation
02/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction; Special Use Authorizations |
| Verizon Communication Site - Datil | Decision Signed Date: 02/04/2025 |
| Forests | Cibola National Forest |
| Districts | Magdalena Ranger District |
| Legal Land Description | T. 1S., R. 11W., Section 2, Lot 11, NMPM |