Project timeline

1
Scoping Start
12/06/2024
2
Decision
02/2025 (Estimated)
3
Implementation
02/2025 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityFacility Improvements/Construction; Special Use Authorizations
Verizon Communication Site - DatilDecision Signed Date: 02/04/2025
ForestsCibola National Forest
DistrictsMagdalena Ranger District
Legal Land DescriptionT. 1S., R. 11W., Section 2, Lot 11, NMPM
Special use management