Replacing approximately 1,000 ft of existing waterline conveying flow from Bear Wallow Spring to the water storage tanks in Upper Soldier Camp cabin area. New line will be 2" HDPE pipe.
Location
Upper Bear Wallow Road and Upper Soldier Camp Road
Project timeline
1
NEPA Start Date
7/17/2026
2
Finding/Decision Date
9/10/2026
NEPA / regulatory detail
| Categorical Exclusion | USDA-28d-USFS |
| Decision Signed Date | 9/10/2026 |