Create a linear shaded fuelbreak consisting of mechanical and hand thinning followed by prescribed fire. Future maintenance would be required.
Location
Located west of U.S. Highway 180 and just north of Catron County Road C-013
Project timeline
1
Scoping Start
09/23/2025
2
Comment Period
10/07/2025
3
Decision
12/2025 (Estimated)
4
Implementation
05/2026 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.3(11) |
| Special Authority | 2021 Infrastructure: Fuel Break Ce |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels) |
| Pueblo Park Fuelbreaks | Decision Signed Date: 12/16/2025 |
| Forests | Gila National Forest |
| Districts | Glenwood Ranger District |
| Legal Land Description | T. 8 S., R. 21 W., Sections 4, 5, 7, 8, 16-18 |