Decision Memo Completed

Forest Road 52 Realignment

Ashley National Forest Uintah, Utah Vernal Ranger District

The project would realign Forest Road (FR) 52 so that it branches off of FR 50, directly south of the Barker Spring Loop cattleguard. We would also replace the associated Little Brush Creek gate with fencing.

Location

Forest Service Road 52 runs along the south ridge of Dutch Charles Draw.

Project timeline

1
Scoping Start
02/28/2025
2
Decision
04/2025 (Estimated)
3
Implementation
06/2025 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (24), 36 Cfr 220.6(E)(24)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityRoad Improvements/Construction; Grazing Structural Improvements
Forest Road 52 RealignmentDecision Signed Date: 04/15/2025
ForestsAshley National Forest
DistrictsVernal Ranger District
Legal Land DescriptionNot Applicable
Grazing managementRoad management