The project would realign Forest Road (FR) 52 so that it branches off of FR 50, directly south of the Barker Spring Loop cattleguard. We would also replace the associated Little Brush Creek gate with fencing.
Location
Forest Service Road 52 runs along the south ridge of Dutch Charles Draw.
Project timeline
1
Scoping Start
02/28/2025
2
Decision
04/2025 (Estimated)
3
Implementation
06/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (24), 36 Cfr 220.6(E)(24) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Improvements/Construction; Grazing Structural Improvements |
| Forest Road 52 Realignment | Decision Signed Date: 04/15/2025 |
| Forests | Ashley National Forest |
| Districts | Vernal Ranger District |
| Legal Land Description | Not Applicable |