The project proposed to install a bottomless culvert across South Fork Bear Creek to provide a safer creek crossing to the trailhead.
Location
The location is at the South Fork of Bear Creek Trailhead off of Forest Service Road 058.
Project timeline
1
Scoping Start
04/22/2025
2
Decision
06/2025 (Estimated)
3
Implementation
09/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (22), 36 Cfr 220.6(E)(22) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management |
| South Fork Bear Creek Bottomless Culvert | Decision Signed Date: 06/06/2025 |
| Forests | Caribou-Targhee National Forest |
| Districts | Palisades Ranger District |
| Legal Land Description | Township 2S, Range 43E, Section 26 |