Emery Telcom is proposing to bury approximately 2,500 ft of fiber line to the Baker Administration site along North Creek Rd, Pinyon Dr.
Location
Along North Creek Road and Pinyon Drive and into the USFS Baker Administration Site.
Project timeline
1
Scoping Start
05/22/2025
2
Decision
06/2025 (Estimated)
3
Implementation
06/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Emery Telcom-Baker Administration Site Utility Project | Decision Signed Date: 06/18/2025 |
| Forests | Manti-Lasal National Forest |
| Districts | Monticello Ranger District |
| Legal Land Description | T33S R23E Sec 35 |