Replace two trail bridges National Forest System Trails 089 and 094 to facilitate safe and consistent stream crossings for all users.
Location
Trail bridges are located on Nick Creek and the NF Buckhorn Creek on existing two-wheeled motorized trails (NFST 089 and NFST 094).
Project timeline
1
Scoping Start
10/01/2023
2
Decision
06/2025 (Estimated)
3
Implementation
08/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Buckhorn Creek Bridge Installation | Decision Signed Date: 06/03/2025 |
| Forests | Payette National Forest |
| Districts | Krassel Ranger District |
| Legal Land Description | T19N, R6E, section 30; T18N, R5E, section 1. |