Environmental Impact Statement On Hold

Southern California Edison Control-Silver Peak 55kV Reliability Project

Inyo National Forest Inyo, California Inyo National Forest All Units

Installation of remote fault indicators, packet routers, and installation of remote switches along with poles replacements.

Location

Silver Canyon, east of Bishop, CA

Project timeline

1
NOI in Federal Register
11/2023 (Estimated)
2
DEIS NOA in Federal Register
03/2024 (Estimated)
3
FEIS NOA in Federal Register
06/2026 (Estimated)
4
Objection Period Start
06/2025 (Estimated)
5
Decision
06/2026 (Estimated)
6
Implementation
07/2026 (Estimated)

NEPA / regulatory detail

Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivitySpecial Use Authorizations
ForestsInyo National Forest
DistrictsWhite Mountain Ranger District
Legal Land DescriptionNot Applicable
Special use management