Decision Memo Developing Proposal

LADWP Long Valley Pole Removal and Pole Replacement Project

Inyo National Forest Mono, California Inyo National Forest All Units

LADWP Utility Maintenance Project:1)removal of poles & replacement of poles in one line and 2)removal of poles & rehab in second line, 3)relinquish poles

Location

LADWP locations of distribution line maintenance work is on a combination of LADWP and INF lands, staring at the Upper Gorge power plant down to the Long Valley Dam, on the White Mtn. Ranger District

Project timeline

1
Scoping Start
04/2024 (Estimated)
2
Decision
07/2024 (Estimated)
3
Implementation
10/2024 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
ForestsInyo National Forest
DistrictsWhite Mountain Ranger District
Legal Land DescriptionNot Applicable
Special use management