Environmental Impact Statement Completed

Meeks Bay Restoration

Lake Tahoe Basin Management Unit El Dorado, California Lake Tahoe Basin Mgt Unit

Restoration of Meeks Creek in Meeks Marina, remove marina, reconstruct Meeks campground, BMPs, pedestrian bridge over Meeks Creek, pathways, beach access, parking improvements, utility upgrades, alternatives for a pier

Location

Meeks Bay Resort and Meeks Bay Campground east of SR89, as well as a short portion of Meeks Creek west of SR89.

Project timeline

1
NOI in Federal Register
09/11/2018
2
DEIS NOA in Federal Register
06/10/2022
3
FEIS NOA in Federal Register
04/05/2024
4
Objection Period Start
04/05/2024
5
Decision
08/2024 (Estimated)
6
Implementation
09/2024 (Estimated)

NEPA / regulatory detail

Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityDeveloped Site Management; Facility Improvements/Construction; Species Habitat Improvements; Heritage Resource Management; Facility Maintenance; Trail Management; Species Population Enhancements; Scenery Management; Watershed Improvements
Final Record of Decision for the Meeks Bay Restoration ProjectDecision Signed Date: 08/12/2024
ForestsLake Tahoe Basin Mgt Unit
DistrictsLake Tahoe Basin Mgt Unit
Legal Land DescriptionNot Applicable
Heritage resource managementFacility managementWildlife, fish, rare plantsWatershed managementRecreation management