We propose to reduce risk of wildfire impacts to communities and critical infrastructure, within Eastside communities with moderate-, high-, or very high-risk wildfire hazard potential. Consistent with the Community Protection Concept, PALS#62128.
Location
The Community Protection %u2013Eastside Project is concentrated on communities located at the eastern border of the Forest that have moderate-, high-, or very high-risk wildfire hazard potential.
Project timeline
1
Scoping Start
05/08/2022
2
Comment Period
10/05/2023
3
Decision
12/2025 (Estimated)
4
Implementation
01/2026 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Biomass; Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Plan Amendment; Noxious Weed Treatments; Road Improvements/Construction; Rangeland Vegetation Improvements; Timber Sales (Salvage); Timber Sales (Green); Watershed Improvements |
| Community Protection - Eastside Project | Decision Signed Date: 12/23/2025 |
| Forests | Plumas National Forest |
| Districts | Plumas National Forest All Units |
| Legal Land Description | Not Applicable |