Yuba County Water Agency is seeking authorization for an 8.7-acre staging and batch plant area to support construction of the Atmospheric River Control (ARC) Spillway Project.
Location
Southwest of New Bullards Bar Dam along Marysville Road on Plumas National Forest (National Forest System lands)
Project timeline
1
Scoping Start
05/23/2025
2
Decision
01/2026 (Estimated)
3
Implementation
03/2026 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Yuba County Water Agency Staging Area and Batch Plant Special Use Permit | Decision Signed Date: 01/16/2026 |
| Forests | Plumas National Forest |
| Districts | Feather River Ranger District |
| Legal Land Description | Not Applicable |