This project will allow the Salyer Heights Water Company to reconstruct critical water supply infrastructure (water tank, raw water lines, and creek diversions) along Shaber Creek that were destroyed in the Campbell Fire.
Location
Water system north of Salyer Heights along Shaber Creek (40.91286, -123.58236).
Project timeline
1
Scoping Start
06/23/2025
2
Decision
07/2025 (Estimated)
3
Implementation
07/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction; Special Use Authorizations |
| Salyer Heights Urgent Drinking Water Needs Project | Decision Signed Date: 07/09/2025 |
| Forests | Six Rivers National Forest |
| Districts | Lower Trinity Ranger District |
| Legal Land Description | T6N R5E Sec 2 & 11 |