Project proposes to repair nine road segments damaged during the February 2020 flood event. Actions include removing landslide debris, repairing/cleaning culverts and ditches, embankment and slope reinforcement.
Location
Forest Roads 25, 2810, 59 and 85.
Project timeline
1
Scoping Start
12/06/2022
2
Decision
11/2023 (Estimated)
3
Implementation
05/2024 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (24), 36 Cfr 220.6(E)(24) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Maintenance; Road Improvements/Construction |
| 2020 Flood Damage ERFO Repairs | Decision Signed Date: 11/20/2023 |
| Forests | Gifford Pinchot National Forest |
| Districts | Cowlitz Ranger District |
| Legal Land Description | Not Applicable |