The project seeks to improve forest health and diversity on approximately 3,225 acres within the Oak Grove Fork Clackamas River watershed.
Location
The planning area is located south of Timothy Lake along the south-eastern boundary of National Forest System lands and encompasses an area of approximately 17,000 acres.
Project timeline
1
Scoping Start
11/25/2024
2
Comment Period
06/17/2025
3
09/24/2025
4
Decision
09/2025 (Estimated)
5
Implementation
05/2026 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Road Maintenance; Timber Sales (Green) |
| Stone Creek Vegetation Management Project | Decision Signed Date: 09/24/2025 |
| Forests | Mt. Hood National Forest |
| Districts | Clackamas River Ranger District |
| Legal Land Description | Not Applicable |