. The project would establish and maintain fuel breaks along the 25 Road that tie together recent Upper Briggs project (signed in 2019) area treatments to the old Taylor-Klondike Fire control lines and Rum Creek Fire contingency lines
Location
T35S 08W, T36S 08W, T37S 08W
Project timeline
1
Scoping Start
01/10/2023
2
Decision
11/2023 (Estimated)
3
Implementation
03/2024 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.3(11) |
| Special Authority | 2021 Infrastructure: Fuel Break Ce |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels) |
| Forests | Rogue River-Siskiyou National Forest |
| Districts | Wild Rivers Ranger District |
| Legal Land Description | Not Applicable |