To replace two lifts Areil and Windsor,which are aging lifts that are no longer repairable. Replacing the two lifts will increase safety and reliability, increase operational efficiency and inprove winter-sport infrastructure.
Location
This project is located on Mt. Ashland on the Siskiyou Mountains Ranger District. Township 40 south Ranger 4 east, Section 16 Willamette Meridian
Project timeline
1
Scoping Start
05/09/2025
2
Decision
03/2026 (Estimated)
3
Implementation
06/2026 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (22), 36 Cfr 220.6(E)(22) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Facility Improvements/Construction |
| Mt. Ashland Ski Lift Replacement | Decision Signed Date: 03/06/2026 |
| Forests | Rogue River-Siskiyou National Forest |
| Districts | Siskiyou Mountains Ranger District |
| Legal Land Description | Not Applicable |