The purpose of this project is to reduce hazardous fuels between the Baker City Watershed and nearby private land.
Location
This project is located in the Baker City Municipal Watershed.
Project timeline
1
Scoping Start
07/21/2022
2
Comment Period
03/09/2024
3
Objection Period Start
03/05/2025
4
Decision
06/2025 (Estimated)
5
Implementation
06/2025 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Road Maintenance; Road Improvements/Construction; Timber Sales (Green); Watershed Improvements |
| Revised Final Baker City Watershed Fuels Management Project | Decision Signed Date: 06/06/2025 |
| Forests | Wallowa-Whitman National Forest |
| Districts | Whitman Ranger District |
| Legal Land Description | T 09 S R 38 E Sec 2,3,4; 9,10,11,12; 13,14,15,16; 22, 23,24; 25,26; 36 T 09 S R 39 E Sec 17, 18, 19, 20, 30, 31 |