Analysis of various projects in the Blackwater watershed in Menifee, Morgan, and Rowan Counties to implement the Forest Plan. These projects were developed from the Blackwater Project Development collaborative effort.
Location
National Forest System Lands in the Blackwater and Paragon drainages in Menifee, Morgan, and Rowan Counties, Kentucky.
Project timeline
1
Scoping Start
05/17/2019
2
Comment Period
11/13/2019
3
Objection Period Start
02/10/2021
4
Decision
09/2021 (Estimated)
5
Implementation
01/2022 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Road Decommissioning; Developed Site Management; Forest Vegetation Improvements; Dispersed Recreation Mgmt.; Species Habitat Improvements; Heritage Resource Management; Facility Maintenance; Trail Management; Noxious Weed Treatments; Road Maintenance; Road Improvements/Construction; Scenery Management; Travel Management; Timber Sales (Green); Watershed Improvements |
| Blackwater Landscape Analysis | Decision Signed Date: 09/03/2021 |
| Forests | Daniel Boone National Forest |
| Districts | Cumberland Ranger District |
| Legal Land Description | Not Applicable |