This project covers refurbishment of small infrastructure and signage across the DBNF. Signs, kiosks, picnic tables, etc. would be replaced or renovated at trailheads, campgrounds, picnic areas and other designated sites across the Forest.
Location
This project would occur at trailhead, campgrounds, road pull-outs, picnic areas and other designated administrative or recreation facility across the Forest.
Project timeline
1
Scoping Start
02/25/2022
2
Decision
04/2022 (Estimated)
3
Implementation
04/2022 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (3), 36 Cfr 220.6(D)(3); 32.12 (5), 36 Cfr 220.6(D)(5) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Facility Improvements/Construction; Dispersed Recreation Mgmt.; Facility Maintenance; Trail Management; Scenery Management; Travel Management; Wilderness Management |
| Decision Decided Date | 04/13/2022 |
| Forests | Daniel Boone National Forest |
| Districts | Daniel Boone National Forest All Units |
| Legal Land Description | Not Applicable |