Several rows of White Pine would be removed at the base of Rebel Trace Dam to allow access to the dam's failing infrastructure. The access will allow crews to make repairs.
Location
Southeast of western end of Forest Service road 1293A, Big Salt Lick Creek Road, along the base of Rebel Trace Dam.
Project timeline
1
Scoping Start
03/17/2023
2
Decision
04/2023 (Estimated)
3
Implementation
03/2023 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (3), 36 Cfr 220.6(D)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Facility Improvements/Construction; Facility Maintenance |
| Decision Decided Date | 04/17/2023 |
| Forests | Daniel Boone National Forest |
| Districts | Cumberland Ranger District |
| Legal Land Description | Not Applicable |