The Southern Appalachian Forests(Cherokee National Forest, George Washington and Jefferson National Forests, National Forests in North Carolina and Chattahoochee - Oconee National Forest seek to implement large landscape watershed resiliency efforts.
Location
The entirety of the George Washington and Jefferson National Forest.
Project timeline
1
Scoping Start
07/01/2024
2
Comment Period
11/2024 (Estimated)
3
Objection Period Start
02/2025 (Estimated)
4
Decision
05/2025 (Estimated)
5
Implementation
06/2025 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Road Decommissioning; Species Habitat Improvements; Noxious Weed Treatments; Species Population Enhancements; Road Maintenance; Road Improvements/Construction; Rangeland Vegetation Improvements; Travel Management; Watershed Improvements |
| Forests | George Washington and Jefferson National Forest |
| Districts | George Washington and Jefferson National Forest All Units |
| Legal Land Description | Not Applicable |