The Lickstone Project is a forest vegetation, wildlife habitat, and watershed management project.
Location
The Lickstone Project Area is comprised of all FS lands of the Pisgah Ranger District East of Lickstone Ridge which is approximately 25 miles southwest of Canton, NC.
Project timeline
1
Scoping Start
05/27/2022
2
Comment Period
06/17/2024
3
Objection Period Start
04/2025 (Estimated)
4
Decision
07/2025 (Estimated)
5
Implementation
10/2025 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 219 (2012) |
| Project Activity | Forest Vegetation Improvements; Species Habitat Improvements; Noxious Weed Treatments; Timber Sales (Green); Watershed Improvements |
| Forests | National Forests In North Carolina |
| Districts | Pisgah Ranger District |
| Legal Land Description | Not Applicable |