The Mena-Oden Ranger District proposes to implement management activities to meet the needs for Dragover Project Area. The intent of these activities is to move the area toward desired conditions described in The Revised Forest Plan.
Location
Primarily North of Mt Ida, Arkansas
Project timeline
1
Scoping Start
12/18/2023
2
Comment Period
03/31/2024
3
Decision
05/2027 (Estimated)
4
Implementation
06/2028 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Species Habitat Improvements; Road Maintenance; Travel Management; Timber Sales (Green); Watershed Improvements |
| Forests | Ouachita National Forest |
| Districts | Oden Ranger District |
| Legal Land Description | Not Applicable |