Vegetation management activities including regeneration and thinning harvests, prescribed burning and control of non-native invasive plants to improve resilience against environmental stressors on 2906 acres of NFS land.
Location
The project area includes a total of 2906 NFS acres comprised of two units in the southwest corner of the Sylamore District
Project timeline
1
Scoping Start
07/11/2025
2
Decision
09/2025 (Estimated)
3
Implementation
10/2026 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.3 (5) |
| Special Authority | Hfra Title Vi: Insect And Disease Projects |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Road Maintenance; Timber Sales (Green) |
| South Unit Project | Decision Signed Date: 09/05/2025 |
| Forests | Ozark-St. Francis National Forests |
| Districts | Sylamore Ranger District |
| Legal Land Description | Not Applicable |