Thin about 269 acres of pine plantations. Prescribed fire on about 1,500 acres. Brushing, planting, and seeding as needed within the project area.
Location
primarily along the Mississippi River between Cass Lake and Lake Winnibigoshish
Project timeline
1
Scoping Start
08/14/2024
2
Decision
05/2025 (Estimated)
3
Implementation
06/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Forest Vegetation Improvements; Species Habitat Improvements; Special Area Management; Timber Sales (Green) |
| Ten Section and Mississippi River UBA Project | Decision Signed Date: 05/30/2025 |
| Forests | Chippewa National Forest |
| Districts | Blackduck Ranger District |
| Legal Land Description | 146N, R29W and 146N, R30W |