Construct and use new timber access roads on NFS lands.
NEPA / regulatory detail
| Categorical Exclusion | USDA-28d-USFS |
| Decision Signed Date | 6/12/2026 |
105 projects with crawled detail · milestones · contacts · documents
Construct and use new timber access roads on NFS lands.
| Categorical Exclusion | USDA-28d-USFS |
| Decision Signed Date | 6/12/2026 |
The old system failed inspection so will be replaced with a new tank in the exact same location as the current system. No trees need to be removed for this project.
| Categorical Exclusion | USDA-28d-USFS |
| Decision Signed Date | 6/11/2026 |
Request to install a new septic system and remove old system.
| Categorical Exclusion | USDA-28d-USFS |
| Decision Signed Date | 6/11/2026 |
Request to add an 18’ by 7’ section to their existing cabin.
| Categorical Exclusion | USDA-28d-USFS |
Request to remove old garage and replace with a 20x20 shed.
| Categorical Exclusion | USDA-28d-USFS |
This project is for prospecting mineral resources (gravel) in areas directly adjacent to the currently active Jessie, Howard, Grave, Whittlestop, and Onigum gravel pits. This effort is intended to evaluate the presence and suitability of additional mineral material that may support Forest activities
| Categorical Exclusion | USDA-32d-USFS |
| Decision Signed Date | 6/4/2026 |
East Ottertail is requesting to install, use, and maintain 5152 feet of fiber optic line. Four pedestals will be installed.
| Categorical Exclusion | USDA-27d-USFS |
Permittee proposes removing a non-compliant septic system and replacing it with a new system. A new 1,650-gallon combination precast concrete tank will be installed along with a lift station, 10’ x 38’ pressure bed drainfield, and connection pipes. No trees will be removed.
| Categorical Exclusion | USDA-28d-USFS |
Permittee proposes replace failing septic system as part of requirements for the upcoming permit renewal. New system will have a 1,500-gallon tank and pressure mound drainfield installed. Old non-compliant drainfield and tank will be removed as part of this project. One 12-inch spruce tree will need
| Categorical Exclusion | USDA-28d-USFS |
| Decision Signed Date | 6/3/2026 |
The purpose of this Environmental Assessment is to evaluate the potential environmental effects of developing, expanding, managing, and closing of select gravel pits within the Chippewa National Forest.
The Blackduck District of the Chippewa National Forest (CPF) is proposing an integrated resource project which seeks to move towards desired conditions throughout the Pennington South Project area on National Forest System (NFS) administered lands.
Permittee proposes to build a temporary, winter only, access road totaling approximately 5,011 feet. The northern section would be approximately 691 feet and the southern section would be approximately 4,320 feet by 12 feet wide
| Categorical Exclusion | USDA-28d-USFS |
| Decision Signed Date | 5/22/2026 |
East Ottertail is requesting to install, use, and maintain 45’ of fiber optic line in a 10’ wide right of way.
| Categorical Exclusion | USDA-27d-USFS |
| Decision Signed Date | 5/19/2026 |
The Forest Service is proposing to amend the Special Use Permit currently held by Enbridge and authorize the three types of decommissioning activities described below, including valve flush or removals, pipeline grouting, and pipeline removal.
The DNR is requesting to use two old skid trails and Sprue Lake HWT to access timber stands for permit B016173.
| Categorical Exclusion | 32.12 (8), 36 Cfr 220.6(D)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Decision Decided Date | 05/13/2026 |
| Forests | Chippewa National Forest |
| Districts | Deer River Ranger District |
| Legal Land Description | T149N R25W Sec 21 & 28 |
Issue road permit to new owner as well as reroute a portion of the existing road.
| Categorical Exclusion | USDA-28d-USFS |
| Decision Signed Date | 5/7/2026 |
East Ottertail is requesting to install, use, and maintain 6065’ of fiber optic line in a 10’ wide right of way. Three Pedestals will be installed. The project is expected to start in Summer 2026. Construction methods include directional boring and plowing.
| Categorical Exclusion | USDA-27d-USFS |
| Decision Signed Date | 5/7/2026 |
MNDNR is requesting to clear and utilize U3289 as part of project 19828. U3289 with be cleared for a width of 18’ and length of 324’. Other roads that will be utilized and covered under a 7700-permit include SLR-S3396, 2130G, SLR-S3395, and 2130.
| Categorical Exclusion | USDA-28d-USFS |
| Decision Signed Date | 4/17/2026 |
Lake Country Power is requesting to install and maintain 8,340’ or 1.58 miles of new line installed in a 30’ ROW way.
| Categorical Exclusion | USDA-27d-USFS |
Road permit to authorize the construction, use and maintenance, and rehabilitation of a temporary haul road across NFS lands to access and harvest state timber sale 20091.
| Categorical Exclusion | USDA-28d-USFS |
Replacement of failed copper facility and installation of fiber optic mainline cable for future use. The cable will be buried at 35 inches. The right-of-way will be approximately 383 feet long and 10 feet wide. The installation is planned to occur in the spring/summer of 2026.
| Categorical Exclusion | USDA-28d-USFS |
| Decision Signed Date | 4/10/2026 |
Road permit to authorize the construction, use and maintenance, and rehabilitation of a temporary haul road across NFS lands to access and harvest state timber sale 20380. The new road would branch off FR2187GA. The new road construction would be 1357 feet in length and 18 feet in width.
| Categorical Exclusion | USDA-28d-USFS |
The State will utilize FR2131, SLR-S5057, and construct 120 feet of new road at the end of SLR-S5057.
| Categorical Exclusion | USDA-28d-USFS |
: Road permit to authorize the construction, use and maintenance, and rehabilitation of a temporary haul road across NFS lands to access and harvest state timber sale 19433. The newly constructed road would branch off of Forest Service Road 2957A.
| Categorical Exclusion | USDA-28d-USFS |
FR2232C branching off FR2232 would be cleared and utilized.
| Categorical Exclusion | USDA-28d-USFS |
The new road would branch off FR3423. It would be 1879 feet in length and 18 feet in width.
| Categorical Exclusion | USDA-28d-USFS |
Permittee proposes to build three different long-term access roads for DNR timber sales and site work. 1) T141N, R25W, S27 totaling approximately 2,200 feet by 18 feet wide following the route of a previous road SLR-S3461. 2) T141N, R28W, S30 totaling approximately 220 feet by 18 feet wide.
| Categorical Exclusion | USDA-28d-USFS |
Permittee proposes to build and maintain a gravel surface private road crossing Chippewa National Forest land to access their private property.
| Categorical Exclusion | USDA-28d-USFS |
University of Minnesota research project using remote sensing techniques and equipment to monitor photosynthesis and transpiration to detect EAB and track spread over time.
| Categorical Exclusion | 32.11, 7 Cfr 1B.3(A) (3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Research And Development |
| Decision Decided Date | 03/20/2026 |
| Forests | Chippewa National Forest |
| Districts | Chippewa National Forest All Units |
| Legal Land Description | Not Applicable |
The project is designed to create quality habitat for the Golden-winged Warbler, American Woodcock, Ruffed Grouse and associated species by reducing the density and age of vegetative species through brush cutting. The project will use TVA CE 30 to authorize.
| Categorical Exclusion | TVA 30 (18 CFR Appendix A to Subpart C of Part 1318(30)) |
This project intends to harvest primarily aspen and paper birch to provide sunlight and growing space to midstory and understory hardwoods and improve stand health and resiliency.
| Categorical Exclusion | 32.2 (12), 36 Cfr 220.6(E)(12) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Forest Vegetation Improvements |
| Forests | Chippewa National Forest |
| Districts | Walker Ranger District |
| Legal Land Description | Not Applicable |
The overhead lines will be removed, and the existing material will be used to fill in the pole holes. The new underground will be located within the existing right of way and no additional tree clearing will be required. The cable will be buried directly into the soil using a vibratory cable plow. T
| Categorical Exclusion | USDA-27d-USFS |
| Decision Signed Date | 3/27/2026 |
Permittee proposes installation of two solar panel arrays.
| Categorical Exclusion | USDA-28d-USFS |
The project is slated to occur in the Summer of 2026. It includes the installation of BD5 Pedestals and approximately 3429 feet of fiber in an existing right-of-way. The ROW will be 33 feet wide. The line will be plowed and directionally drilled.
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Chippewa National Forest |
| Districts | Walker Ranger District |
| Legal Land Description | Not Applicable |
Road Permit for the use and maintenance
| Categorical Exclusion | USDA-28d-USFS |
| Decision Signed Date | 2/10/2026 |
Use and maintenance of a private road crossing NFS lands.
| Categorical Exclusion | USDA-28d-USFS |
| Decision Signed Date | 1/6/2026 |
Install 960 feet of fiber optic cable to the visitor center, workshop, and lodge including three connection boxes.
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Chippewa National Forest |
| Districts | Deer River Ranger District |
| Legal Land Description | Not Applicable |
Replace the warehouse roof at the Supervisor's Office
| Categorical Exclusion | 32.12 (3), 36 Cfr 220.6(D)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction; Facility Maintenance |
| Decision Decided Date | 12/10/2025 |
| Forests | Chippewa National Forest |
| Districts | Chippewa National Forest All Units |
| Legal Land Description | Not Applicable |
Project proposes to remove 2 gates and a rock barricade, allowing motorized access to an overlook, and access to a previously closed segment of road. This segment will be added back to the Forest transportation system and MVUM.
| Categorical Exclusion | 32.2 (23), 36 Cfr 220.6(E)(23) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Maintenance; Travel Management |
| Forests | Chippewa National Forest |
| Districts | Blackduck Ranger District |
| Legal Land Description | T.146N, R.30W, Sec. 21, S1/2NE |
Replace two single pane windows, replace cedar siding, and replace two window awnings.
| Categorical Exclusion | 32.12 (5), 36 Cfr 220.6(D)(5) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Decision Decided Date | 06/20/2024 |
| Forests | Chippewa National Forest |
| Districts | Deer River Ranger District |
| Legal Land Description | T146N, R27W, Section 29 |
Installation and maintenance of 3,376 feet of line using vibratory plow or directional bore. Much of the line listed is existing and is planned to be upgraded to better meet the demands. This project is with the reservation boundary
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Chippewa National Forest |
| Districts | Walker Ranger District |
| Legal Land Description | T141N R30W Sec 3 and R29W Sec 1 |
Road permit to authorize the construction, use and maintenance, and rehabilitation of a temporary haul road across NFS lands to access and harvest state timber sale 20382. The newly constructed road would branch off of Forest Service Road 3406A.
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Chippewa National Forest |
| Districts | Blackduck Ranger District |
| Legal Land Description | Not Applicable |
Rebuilding stairway down to the lake
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Chippewa National Forest |
| Districts | Blackduck Ranger District |
| Legal Land Description | T146N, R31W, Section 36 |
Rebuilding stairway down to lake.
| Categorical Exclusion | 32.12 (5), 36 Cfr 220.6(D)(5) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Decision Decided Date | 09/08/2025 |
| Forests | Chippewa National Forest |
| Districts | Blackduck Ranger District |
| Legal Land Description | T146N, R31W, Section 34 |
Building a new deck
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Chippewa National Forest |
| Districts | Blackduck Ranger District |
| Legal Land Description | T145N, R29W, Section 2 |
Septic installation and well replacement. Old outhouse and old well to be abandoned
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Chippewa National Forest |
| Districts | Walker Ranger District |
| Legal Land Description | T142N, R31W, Sect. 14. |
Decision to approve the CPF System Road Maintenance Project which includes forest wide road maintenance activities within the existing roadway and adjacent clearing zones.
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Forest Vegetation Improvements |
| Forests | Chippewa National Forest |
| Districts | Chippewa National Forest All Units |
| Legal Land Description | Not Applicable |
Recreation residence cabin addition of a new attached garage and removal of the existing detached garage. Within LLBO Reservation.
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Chippewa National Forest |
| Districts | Deer River Ranger District |
| Legal Land Description | T147N, R27W, Section 36 |
The use of prescribed fire and mechanical treatments to restore fire-dependent ecosystems and wildlife habitats on 1913 acres of national forest system lands, within the proclamation boundary of the Leech Lake Band of Ojibwe Indian Reservation.
| Categorical Exclusion | 32.2 (25), 36 Cfr 220.6(E)(25) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Forest Vegetation Improvements |
| Forests | Chippewa National Forest |
| Districts | Chippewa National Forest All Units |
| Legal Land Description | Not Applicable |
Installation and maintenance of 53,211 ft of line to be installed using a vibratory plow or directional bore under roadways and water ways. Much of the line is existing and is to be upgraded to better meet demands. partly within reservation.
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Chippewa National Forest |
| Districts | Walker Ranger District |
| Legal Land Description | Not Applicable |
Establishment of Goose Lake gravel pit near Mud/Goose Lake south of Ball Club Mn. Not on LLBO Reservation
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations; Minerals Or Geology Plans Of Operations; Road Maintenance |
| Forests | Chippewa National Forest |
| Districts | Deer River Ranger District |
| Legal Land Description | SW 1/4 NW 1/4 S6, T143, R25N |
.25-mile interpretive trail. The trails width of approximately 8ft would involve clearing brush and small trees. portions of the trail will be widened for Interpretive displays. Project will avoid sensitive areas involving Lady Slippers, or other spe
| Categorical Exclusion | 32.2 (22), 36 Cfr 220.6(E)(22) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Forests | Chippewa National Forest |
| Districts | Blackduck Ranger District |
| Legal Land Description | T146, R30W, Section 15 |
The trail reroute section is 10 miles. Decommission old NCT segments. Constructing two parking areas and two dispersed campsites, which will include fire grates, wilderness latrines, and tent pads.
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Dispersed Recreation Mgmt.; Trail Management |
| Forests | Chippewa National Forest |
| Districts | Deer River Ranger District |
| Legal Land Description | West termini T 142N, R 25W, section 21. East termini T 143N, R 25W, section 25 |
Thin about 269 acres of pine plantations. Prescribed fire on about 1,500 acres. Brushing, planting, and seeding as needed within the project area.
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Forest Vegetation Improvements; Species Habitat Improvements; Special Area Management; Timber Sales (Green) |
| Forests | Chippewa National Forest |
| Districts | Blackduck Ranger District |
| Legal Land Description | 146N, R29W and 146N, R30W |
Replace rotting deck boards with new boards brown in color.
| Categorical Exclusion | 32.12 (5), 36 Cfr 220.6(D)(5) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Decision Decided Date | 03/21/2025 |
| Forests | Chippewa National Forest |
| Districts | Deer River Ranger District |
| Legal Land Description | T147N, R27W, Section 22 |
Install new heat pump/air conditioning minisplit unit on recreation residence cabin.
| Categorical Exclusion | 32.12 (5), 36 Cfr 220.6(D)(5) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Decision Decided Date | 03/21/2025 |
| Forests | Chippewa National Forest |
| Districts | Deer River Ranger District |
| Legal Land Description | T147N, R27W, Section 27; on LLBO Reservation |
Authorize reoccurrence of equipment to excavate channel bottom sediment approximately 2ft in depth, 3-6ft in width, and 50-150ft in length. Sediment spoils will be deposited adjacent to previous spoils sites.
| Categorical Exclusion | 32.12 (5), 36 Cfr 220.6(D)(5) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Facility Maintenance |
| Decision Decided Date | 02/05/2025 |
| Forests | Chippewa National Forest |
| Districts | Blackduck Ranger District; Deer River Ranger District |
| Legal Land Description | T147N, R27W, Sec. 28; T146N, R29W, Sec. 35 |
MN DNR is requesting to create of a temporary road for access across FS land. Location is depicted in the map below and I've requested the proposed route to be flagged in the field.
| Categorical Exclusion | 32.12 (8), 36 Cfr 220.6(D)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Decision Decided Date | 01/23/2025 |
| Forests | Chippewa National Forest |
| Districts | Deer River Ranger District |
| Legal Land Description | T144N R27W Sec 27 |
MN DNR is requesting a new temporary access off Alder Rd. to their harvest area depicted in the map below.
| Categorical Exclusion | 32.12 (8), 36 Cfr 220.6(D)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Decision Decided Date | 01/23/2025 |
| Forests | Chippewa National Forest |
| Districts | Deer River Ranger District |
| Legal Land Description | T58N R27W Sec 11, 14, & 15 |
MN DNR is requesting two new temporary roads to access timber sale. The locations are depicted in the map and requested the proposed route to be flagged in the field. Within Reservation.
| Categorical Exclusion | 32.12 (8), 36 Cfr 220.6(D)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Decision Decided Date | 01/23/2025 |
| Forests | Chippewa National Forest |
| Districts | Deer River Ranger District |
| Legal Land Description | T144N R27W Sec 3 , 4, T145N R27W Sec 33 , 32 |
MN DNR is requesting a new temporary access off Forest Road 2040 to their harvest area depicted in the map below.
| Categorical Exclusion | 32.12 (8), 36 Cfr 220.6(D)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Decision Decided Date | 01/23/2025 |
| Forests | Chippewa National Forest |
| Districts | Deer River Ranger District |
| Legal Land Description | T147N R26W Sec 2} |
MN DNR is requesting use of an old skid trail off FR2441C for 1.4 miles to access their southerly harvest area and the northerly harvest area will be accessed using SLR-S117
| Categorical Exclusion | 32.12 (8), 36 Cfr 220.6(D)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Decision Decided Date | 10/10/2024 |
| Forests | Chippewa National Forest |
| Districts | Blackduck Ranger District |
| Legal Land Description | T150N R26W Sec 34 |
MN DNR is requesting access on Forest Service U1199
| Categorical Exclusion | 32.12 (8), 36 Cfr 220.6(D)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Decision Decided Date | 10/10/2024 |
| Forests | Chippewa National Forest |
| Districts | Blackduck Ranger District |
| Legal Land Description | T149N R27W Sec 34 |
Stony Point Day Use Boat Landing is for visitor day use. This boat landing need to be dredged so visitors can safely get their boats into the harbors. We will dump the dredge material in the stony brush disposal site.
| Categorical Exclusion | 32.11, 7 Cfr 1B.3(A) (3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management |
| Decision Decided Date | 10/10/2024 |
| Forests | Chippewa National Forest |
| Districts | Walker Ranger District |
| Legal Land Description | Township: 142, Range: 30, Section: 10 |
A temporary road and landing area has been requested to access a state timber sale off the end of Forest Road 3424 until arriving at the State/FS property boundary. Approximate road location is depicted in the attached map
| Categorical Exclusion | 32.12 (8), 36 Cfr 220.6(D)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Decision Decided Date | 10/09/2024 |
| Forests | Chippewa National Forest |
| Districts | Blackduck Ranger District |
| Legal Land Description | T147N R25W Sec 30 |
A new temporary road has been requested to access a state timber sale off of Forest Road 2957A until arriving at the State/FS property boundary. Approximate road location is depicted in the attached map.
| Categorical Exclusion | 32.12 (8), 36 Cfr 220.6(D)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Decision Decided Date | 10/09/2024 |
| Forests | Chippewa National Forest |
| Districts | Blackduck Ranger District |
| Legal Land Description | T145N R29W Sec 17&18 |
A new temporary road has been requested to access a state timber sale off of State Logging Road S5057 until arriving at the State/FS property boundary. Approximate road location is depicted in the attached map.
| Categorical Exclusion | 32.12 (8), 36 Cfr 220.6(D)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Decision Decided Date | 10/09/2024 |
| Forests | Chippewa National Forest |
| Districts | Walker Ranger District |
| Legal Land Description | T144N R29W Sec 13&14 |
A new temporary road has been requested to access a state timber sale off of State Logging Road S5057 until arriving at the State/FS property boundary. Approximate road location is depicted in the attached map.
| Categorical Exclusion | 32.12 (8), 36 Cfr 220.6(D)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Decision Decided Date | 10/09/2024 |
| Forests | Chippewa National Forest |
| Districts | Walker Ranger District |
| Legal Land Description | T144N R29W Sec 13&14 |
A temporary road has been requested to access a state timber sale off of Forest Road 2171F. Approximate Road location is depicted in the attached map.
| Categorical Exclusion | 32.12 (8), 36 Cfr 220.6(D)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Decision Decided Date | 10/09/2024 |
| Forests | Chippewa National Forest |
| Districts | Walker Ranger District |
| Legal Land Description | T145N R30W Sec 2 |
Removing old storage buildings and building a new shed as well as installing a septic system.
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Chippewa National Forest |
| Districts | Blackduck Ranger District |
| Legal Land Description | T146N, R31W, Section 34 |
Rebuilding boathouse after a tree fell on it during a wind event and the removal of two other nearby trees.
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Chippewa National Forest |
| Districts | Blackduck Ranger District |
| Legal Land Description | T145N, R31W, Section 2 |
This project will include vegetation management. The project is within the exterior boundary of the Leech Lake Band of Ojibwe reservation boundary.
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Developed Site Management; Forest Vegetation Improvements; Research And Development; Travel Management; Timber Sales (Green); Watershed Improvements |
| Forests | Chippewa National Forest |
| Districts | Blackduck Ranger District; Deer River Ranger District |
| Legal Land Description | Section within the following townships T146N/R26W, R27W; T147N/R26W, R27W; T148N/R26W, R27W, T28W; T149N/R26W,R27W;T150N/R27W, R28W |
A temporary road has been requested across Forest Service land to access a State timber sale. Approximate road location is depicted in the map below.
| Categorical Exclusion | 32.12 (8), 36 Cfr 220.6(D)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Decision Decided Date | 09/13/2024 |
| Forests | Chippewa National Forest |
| Districts | Deer River Ranger District |
| Legal Land Description | T148N R26W Sec 9 |
Potlatch Deltic is requesting summer/winter access to a state timber sale that requires a temporary road across FS land.
| Categorical Exclusion | 32.12 (8), 36 Cfr 220.6(D)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Decision Decided Date | 09/13/2024 |
| Forests | Chippewa National Forest |
| Districts | Deer River Ranger District |
| Legal Land Description | T147N R26W Sec 18 |
Fishing tournament weigh in for up to 20 boats and people at East Seelye Bay Campground Beach/Picnic Area for one hour.
| Categorical Exclusion | 32.12 (12), 36 Cfr 220.6(D)(12) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Decision Decided Date | 09/13/2024 |
| Forests | Chippewa National Forest |
| Districts | Deer River Ranger District |
| Legal Land Description | T147N, R27W, Section 22 |
Permittee proposes to maintain approximately 3,800 feet of existing Forest Road 3756B, Imperial Road, by adding gravel and grading surface. Road width will remain unchanged.
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Decision Decided Date | 06/20/2024 |
| Forests | Chippewa National Forest |
| Districts | Deer River Ranger District |
| Legal Land Description | T58N, R25W, Section 4 |
A current snowmobile trail has drifted off it's original designated route and now encroaches on private property. This project aims to clear trees and brush to put the route back onto it's designated path and buffer the trail from the adjacent lands.
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Decision Decided Date | 05/17/2024 |
| Forests | Chippewa National Forest |
| Districts | Blackduck Ranger District |
| Legal Land Description | T149, R28W, Section 06, and T150, R28W |
A current snowmobile trail has drifted off it's original designated route and now encroaches on private property. This project aims to clear trees and brush to put the route back onto it's designated path and buffer the trail from the adjacent lands.
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Decision Decided Date | 05/17/2024 |
| Forests | Chippewa National Forest |
| Districts | Blackduck Ranger District |
| Legal Land Description | T149, R28W, Section 06, and T150, R28W |
Dredging the three harbors associated with the Stony Point Campground. dredging material will be deposited at a USFS site.
| Categorical Exclusion | 32.12 (5), 36 Cfr 220.6(D)(5) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management |
| Decision Decided Date | 04/10/2024 |
| Forests | Chippewa National Forest |
| Districts | Walker Ranger District |
| Legal Land Description | T142, R30, Sec 10 |
Permittee proposes to maintain approximately 1,500 feet of an existing Forest Road 2478A Spur A, Frazer Road Spur A, by adding gravel, grading, and plowing in the winter to access property. Does not include road expansion.
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Decision Decided Date | 12/13/2023 |
| Forests | Chippewa National Forest |
| Districts | Deer River Ranger District |
| Legal Land Description | T146N, R25W, Section 31 |
Removal of old holding tank and installation of new septic system. Within LLBO reservation boundary.
| Categorical Exclusion | 32.12 (5), 36 Cfr 220.6(D)(5) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Decision Decided Date | 12/04/2023 |
| Forests | Chippewa National Forest |
| Districts | Walker Ranger District |
| Legal Land Description | T142N, R30W, Section 10 |
Road permit to access and maintain FR2082AA, Lille Vermillion Dr NE to access private property.
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Decision Decided Date | 12/04/2023 |
| Forests | Chippewa National Forest |
| Districts | Deer River Ranger District |
| Legal Land Description | T143N, R25W, Section 22 |
Reissuing a special use road permit on an existing road, FR3102
| Categorical Exclusion | 32.12 (11), 36 Cfr 220.6(D)(11) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Decision Decided Date | 12/04/2023 |
| Forests | Chippewa National Forest |
| Districts | Walker Ranger District |
| Legal Land Description | T142N, R28W, Section 35 |
Permittee proposes to re-roof cabins 3, 4, 8, 9, and the boat house using Atlas Castlebrook, Weathered Wood color, architectural shingles. All these roofs sustained wind damage this year.
| Categorical Exclusion | 32.12 (5), 36 Cfr 220.6(D)(5) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Decision Decided Date | 12/04/2023 |
| Forests | Chippewa National Forest |
| Districts | Blackduck Ranger District |
| Legal Land Description | T145N, R30W, Section 18 |
replacement of window in cabin
| Categorical Exclusion | 32.12 (5), 36 Cfr 220.6(D)(5) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Decision Decided Date | 12/04/2023 |
| Forests | Chippewa National Forest |
| Districts | Walker Ranger District |
| Legal Land Description | T142N, R31W, Section 14 |
Building a new 140 sq ft deck at a recreation residence cabin
| Categorical Exclusion | 32.12 (5), 36 Cfr 220.6(D)(5) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Decision Decided Date | 12/04/2023 |
| Forests | Chippewa National Forest |
| Districts | Walker Ranger District |
| Legal Land Description | T142N, R31W, Section 14 |
Disregard: Duplicate Project
| Categorical Exclusion | 32.12 (3), 36 Cfr 220.6(D)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Decision Decided Date | 09/28/2023 |
| Forests | Chippewa National Forest |
| Districts | Blackduck Ranger District |
| Legal Land Description | Not Applicable |
Removal of live and dead standing trees and woody debris within 10ft of the fence surrounding the Stoney Point Campground equipment storage area to prevent further damage from falling trees.
| Categorical Exclusion | 32.12 (3), 36 Cfr 220.6(D)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Maintenance |
| Decision Decided Date | 08/17/2023 |
| Forests | Chippewa National Forest |
| Districts | Walker Ranger District |
| Legal Land Description | T.142N., R.30W., Sec. 3 |
MN DNR is planning on setting up 30 game cameras within the Chippewa NF boundary for deer density surveys.
| Categorical Exclusion | 32.12 (12), 36 Cfr 220.6(D)(12) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Decision Decided Date | 06/17/2026 |
| Forests | Chippewa National Forest |
| Districts | Deer River Ranger District |
| Legal Land Description | Not Applicable |
Road Permit Reissue-Johnson Lake Road Association MAR597003. Not on LLBO reservation.
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4); 32.12 (11), 36 Cfr 220.6(D)(11) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Decision Decided Date | 07/13/2022 |
| Forests | Chippewa National Forest |
| Districts | Deer River Ranger District |
| Legal Land Description | Not Applicable |
Replacement of window with BB damage
| Categorical Exclusion | 32.12 (5), 36 Cfr 220.6(D)(5) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Decision Decided Date | 06/15/2022 |
| Forests | Chippewa National Forest |
| Districts | Walker Ranger District |
| Legal Land Description | T145N, R31W Section 22 |
Outhouse Relocation - Permit holder is requesting to move their current outhouse to a new location on a new slab and make repairs needed to continue utilizing the same building structure
| Categorical Exclusion | 32.12 (5), 36 Cfr 220.6(D)(5) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Decision Decided Date | 06/14/2022 |
| Forests | Chippewa National Forest |
| Districts | Blackduck Ranger District |
| Legal Land Description | T142N, R31W, Sec. 14 |
MN DNR wishes to set up 12 game cameras around Lake Winnibigoshish to monitor anglers.
| Categorical Exclusion | 32.12 (12), 36 Cfr 220.6(D)(12) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Decision Decided Date | 01/04/2022 |
| Forests | Chippewa National Forest |
| Districts | Blackduck Ranger District; Deer River Ranger District |
| Legal Land Description | Not Applicable |
Dredge harbor utilizing a backhoe and then hauling sand to a site down Stony Point Camp Rd.
| Categorical Exclusion | 32.12 (5), 36 Cfr 220.6(D)(5) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Decision Decided Date | 11/18/2021 |
| Forests | Chippewa National Forest |
| Districts | Walker Ranger District |
| Legal Land Description | T142N, R30W, Sec 10 |
MNDNR is requesting to improve FR2350. They want to improve approximately 3600 feet of existing minimum maintenance road from a width of 9 feet to 12 feet and clear brush and trees to a width of 18 feet.
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Decision Decided Date | 08/17/2021 |
| Forests | Chippewa National Forest |
| Districts | Deer River Ranger District |
| Legal Land Description | T60N, R26W, Section 1 |
Road permit reissue
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Decision Decided Date | 09/02/2021 |
| Forests | Chippewa National Forest |
| Districts | Blackduck Ranger District |
| Legal Land Description | T147N, R30W, Sections 6, 7, 18 and T141N, R31W, Sections 1, 12 |
Road permit reissue for the use and maintenance of an existing forest road, U5189. No projects are being requested at this time and all activities fall within the scope of the standard permit.WAL402204
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Decision Decided Date | 09/02/2021 |
| Forests | Chippewa National Forest |
| Districts | Walker Ranger District |
| Legal Land Description | T141N, R31W, Section 30 |
Issue a road permit to add gravel to U1117.
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Decision Decided Date | 08/23/2021 |
| Forests | Chippewa National Forest |
| Districts | Blackduck Ranger District |
| Legal Land Description | T149N, R28W, Section 5 |
Road permit for the use and maintenance of an existing forest road, FR3518 aka Briezin Road. DER102100
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Decision Decided Date | 08/17/2021 |
| Forests | Chippewa National Forest |
| Districts | Deer River Ranger District |
| Legal Land Description | T58N, R25W, Section 2 |
Reissue a special use road permit for FR2540
| Categorical Exclusion | 32.12 (11), 36 Cfr 220.6(D)(11) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Decision Decided Date | 06/17/2026 |
| Forests | Chippewa National Forest |
| Districts | Walker Ranger District |
| Legal Land Description | T142N, R27W, Section 22, 21 |
The project includes construction of 244 feet of rock riprap shoreline protection at the Norway Beach Resort along the shoreline of Cass Lake. The project is within the LLBO
| Categorical Exclusion | 32.2 (7), 36 Cfr 220.6(E)(7) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Watershed Improvements |
| Forests | Chippewa National Forest |
| Districts | Blackduck Ranger District |
| Legal Land Description | Not Applicable |
FR2112B Road Permit Reissue. This is not within the boundary of the Leech Lake Band of Ojibwe reservation
| Categorical Exclusion | 32.12 (10) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Decision Decided Date | 12/15/2020 |
| Forests | Chippewa National Forest |
| Districts | Deer River Ranger District |
| Legal Land Description | T142N R25W Section 4 |
Road permit reissue for FR2632A. Project is within LLBO boundary.
| Categorical Exclusion | 32.12 (10) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Decision Decided Date | 12/14/2020 |
| Forests | Chippewa National Forest |
| Districts | Walker Ranger District |
| Legal Land Description | Not Applicable |
Road permit reissue for FR3402A and FR3402
| Categorical Exclusion | 32.12 (10) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Decision Decided Date | 12/14/2020 |
| Forests | Chippewa National Forest |
| Districts | Blackduck Ranger District |
| Legal Land Description | Not Applicable |
Road permit reissue for a private road on NFS lands. Project is within LLBO Reservation lands.
| Categorical Exclusion | 32.12 (10) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Decision Decided Date | 12/08/2020 |
| Forests | Chippewa National Forest |
| Districts | Walker Ranger District |
| Legal Land Description | Not Applicable |