Establishment of Goose Lake gravel pit near Mud/Goose Lake south of Ball Club Mn. Not on LLBO Reservation
Location
From Ball Club Mn, Travel south on County Road 18 for 5.25 Miles. Where County Road 18 turns east, continue south on 72nd Ave. Travel south on 72nd Ave for 1.6 miles. Turn east on to FS2329 and travel for approximately1/4 mile ending at project site.
Project timeline
1
Scoping Start
06/28/2024
2
Decision
08/2024 (Estimated)
3
Implementation
09/2024 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations; Minerals Or Geology Plans Of Operations; Road Maintenance |
| Forests | Chippewa National Forest |
| Districts | Deer River Ranger District |
| Legal Land Description | SW 1/4 NW 1/4 S6, T143, R25N |