Enbridge plans to conduct electrical work to connect the pipeline system to a newly installed transformer associated with a powerline relocation at Milepost 975.6 during the fall of 2026.
Location
Old Six Mile Lake Road
Project timeline
1
NEPA Start Date
8/17/2026
2
Finding/Decision Date
8/24/2026
NEPA / regulatory detail
| Categorical Exclusion | USDA-27d-USFS |
| Decision Signed Date | 8/24/2026 |