The septic did not pass the state requirements and needs to be replaced.
Location
East Side of Pike Bay along FR 2137
Project timeline
1
NEPA Start Date
7/27/2026
2
Finding/Decision Date
8/6/2026
NEPA / regulatory detail
| Categorical Exclusion | USDA-28d-USFS |
| Decision Signed Date | 8/6/2026 |