The Appalachian Trail/Long Trail (AT/LT) Homerstone Bridge crossing Homer Stone Brook was overtopped in 2011 and 2023. The foundation is eroded and the trail was washed out. Proposal would provide new trail tread and a safe structure to cross brook.
Location
Town of Wallingford
Project timeline
1
Scoping Start
01/30/2025
2
Decision
09/2025 (Estimated)
3
Implementation
07/2026 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management; Watershed Improvements |
| Appalachian Trail/Long Trail (AT/LT) Homerstone Bridge Replacement | Decision Signed Date: 09/10/2025 |
| Forests | Green Mountain And Finger Lakes National Forests |
| Districts | Manchester Ranger District |
| Legal Land Description | Not Applicable |