Decision Memo Completed

Green Mountain Power Woodstock Powerline Reconstruction

Green Mountain and Finger Lakes National Forests Windsor, Vermont Green Mountain And Finger Lakes National Forest All Units

Issuance of a 5-year permit to retire and remove existing utility poles and lines along Vermont Route 12 in Woodstock.

Location

Town of Woodstock

Project timeline

1
Scoping Start
01/08/2025
2
Decision
04/2025 (Estimated)
3
Implementation
06/2025 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (2), 36 Cfr 220.6(E)(2)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Green Mountain Power Woodstock Powerline ReconstructionDecision Signed Date: 04/18/2025
ForestsGreen Mountain And Finger Lakes National Forests
DistrictsRochester Ranger District
Legal Land DescriptionNot Applicable
Special use management