Replace an existing culvert along Murray Hollow Road with a bottomless bridge structure to enhance aquatic organism passage and flood resiliency. Includes in-stream work to mimic stream elevations above and below the structure.
Location
Town of Arlington
Project timeline
1
Scoping Start
04/04/2025
2
Decision
05/2025 (Estimated)
3
Implementation
08/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (18), 36 Cfr 220.6(E)(18) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Improvements/Construction; Watershed Improvements |
| Murray Hollow Aquatic Organism Passage (AOP) | Decision Signed Date: 05/07/2025 |
| Forests | Green Mountain And Finger Lakes National Forests |
| Districts | Manchester Ranger District |
| Legal Land Description | Not Applicable |