Decision Memo Completed

Cloverland Project 202

Hiawatha National Forest Chippewa, Michigan Sault Ste. Marie Ranger District

This project proposes adding a new line to the existing master special use permit, that will connect two critical substations allowing broader backup coverage of powered service when emergencies or line outages arise across currently isolated circuit

Location

create a create a circuit tie between Trout Lake and Eckerman substations. Installation will consist of approximately three miles of 3%u0278 #350MCM concentric line in a 6" HDPE conduit.

Project timeline

1
Scoping Start
05/05/2025
2
Decision
05/2025 (Estimated)
3
Implementation
05/2025 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityElectric Transmission; Facility Improvements/Construction; Special Use Authorizations
Cloverland Project 202Decision Signed Date: 05/30/2025
ForestsHiawatha National Forest
DistrictsSault Ste. Marie Ranger District
Legal Land DescriptionNot Applicable
Special use management