0910 Road Permit 2026 Developing Proposal
Categorical Exclusion · St. Ignace Ranger District · updated 6/17/2026 · decision 7/2026 (Estimated)
Section 32, T41N, R 4W · Mackinac, Michigan

Proponent has requested a right-of-way authorization for an existing road to allow all-season vehicle access for the reasonable use and enjoyment of his private property.

Special use management
NEPA Start Date
1/5/2026
Finding/Decision Date
Julia Hall · julia.hall@usda.gov
NEPA / regulatory detail
Categorical ExclusionUSDA-28d-USFS
Environmental Assessment · Munising Ranger District · updated 6/10/2026
See PALS #67452, project maps in Pinyon Public Project Record · Alger; Chippewa; Delta; Schoolcraft, Michigan

Long-term vegetation management of Jack Pine ecosystems. Multi-year forest-wide project designed to identify, develop, and maintain jack pine ecosystem for Kirtland's warbler habitat, and maintain or create fuelbreaks for neighboring infrastructure.

Fuels managementVegetation management (other than forest products)Wildlife, fish, rare plants
NEPA Start Date
4/3/2024
Finding/Decision Date
5/27/2026
Project documents
Christopher Leeseberg · christopher.leeseberg@usda.gov
NEPA / regulatory detail
Decision Signed Date5/27/2026
Categorical Exclusion · Manistique Ranger District · updated 6/10/2026
Indian River Campground: Lat: 46.15436889 Long: -86.40376611. Colwell Lake Campground-across from site 18: Lat: 46.22147278 Long: -86.43363833 · Schoolcraft, Michigan

Removal and replacement of 2 concrete outhouse and vaults, and accessible pathways, one each, at Indian River and Colwell Lake Campgrounds. To view documents related to this proposal, copy and paste link to internet browser: https://usfs-public.box.com/s/oke451p99wz333yj8nmzi1pba1dk8gig

Recreation management
NEPA Start Date
3/11/2026
Finding/Decision Date
4/29/2026
Melissa Buzzard · melissa.buzzard@usda.gov
NEPA / regulatory detail
Categorical ExclusionUSDA-44d-USFS
Decision Signed Date4/29/2026
Categorical Exclusion · Munising Ranger District · updated 5/18/2026 · decision 11/2026 (Estimated)
For better maps, see project documents. Rock River Canyon Wilderness - Trail to Ice Caves · Alger, Michigan

Develop formal access to the Eben Ice Caves through the establishment of a National Forest System trail from the ice caves to both the public and private access sites.

Recreation managementSpecial area management
NEPA Start Date
5/15/2026
Finding/Decision Date
Project documents
Andrew Rogers · andrew.rogers@usda.gov
NEPA / regulatory detail
Categorical ExclusionUSDA-26d-USFS
Decision Memo · Munising Ranger District · updated 4/10/2026
Grand Island National Recreation Area; Murray Bay Day Use Area and Campsites, Juniper Flats Groupsite, and Mather Lodge Historic Site · Alger, Michigan

Make improvements to the existing water systems at Murray Bay, Juniper Flats, Mather Lodge, and Farrell Cottage. Installation of new wellhouses and associate infrastructure at Murray Bay and Juniper Flats, and upgrades at Mather and Farrell

Recreation managementSpecial area managementFacility management
Scoping Start
09/04/2024
Decision
04/2026 (Estimated)
Implementation
05/2026 (Estimated)
Project documents
Brian Hinch · brianhinch@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (21), 36 Cfr 220.6(E)(21); 32.2 (22), 36 Cfr 220.6(E)(22)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityDeveloped Site Management; Special Area Management
ForestsHiawatha National Forest
DistrictsMunising Ranger District
Legal Land DescriptionGrand Island NRA - Murray Bay Day T47N, R19W, Sec 14. Juniper Flats T47N, R19W, Sec 9. Mather Lodge T48N, R19W, Sec 4
Categorical Exclusion · St. Ignace Ranger District · updated 4/8/2026
Mackinac and Chippewa Counties, St. Ignace and Sault Ste. Marie Districts · Chippewa; Mackinac, Michigan

Install one holding tank at the host site in Bay View Campground and two holding tanks in Brevoort Lake Campground, one at each host site.

Recreation managementWatershed management
NEPA Start Date
2/23/2026
Finding/Decision Date
4/7/2026
Kari Thompson · kari.thompson@usda.gov
NEPA / regulatory detail
Categorical ExclusionUSDA-44d-USFS
Decision Signed Date4/7/2026
Categorical Exclusion · St. Ignace Ranger District · updated 4/1/2026
Located in Section 18, T42N, R4W, on FR-3445 about 700 feet West of Mackinac Trail. It is just north of the Carp River Campground. · Mackinac, Michigan

The St. Ignace Ranger District proposes to remove the existing 17-foot-wide by 90-foot-long, five span timber bridge, by the name of Carp River Bridge 3445-0.1, on FR3445 which spans the Carp River, and rehabilitate the riverbanks.

Road managementWatershed management
NEPA Start Date
1/9/2026
Finding/Decision Date
3/31/2026
Todd Kenyon · todd.kenyon@usda.gov
NEPA / regulatory detail
Categorical ExclusionUSDA-42d-USFS
Decision Signed Date3/31/2026
Categorical Exclusion · Manistique Ranger District · updated 1/8/2026
FR2109 between H-13 and FR2224 · Delta, Michigan

Upgrade 1.5 miles of FR2109 from operation maintenance level (OML) 3 to OML 4, by widening the surface to 20-22 feet, upgrading the surface and culverts, and improving the ditches. https://usfs.app.box.com/folder/359621917628

Forest productsRoad management
NEPA Start Date
1/5/2026
Finding/Decision Date
1/8/2026
Kate Johnson · kate.johnson@usda.gov
NEPA / regulatory detail
Categorical ExclusionUSDA-46d-USFS
Decision Signed Date1/8/2026
Decision Memo · Hiawatha National Forest All Units · updated 12/1/2025
Two Recreation Residence Tracts are involved, High Banks (East Zone) and Sturgeon River (West Zone). Line near RACO proposed, and Forest Service Campgrounds Colwell and Bear Lake. · Alger; Chippewa; Delta; Schoolcraft, Michigan

Install additional underground fiber for approximately 13.6 miles within a 10-foot right of way as an amendment to their existing authorization.

Special use management
Scoping Start
09/16/2025
Decision
10/2025 (Estimated)
Implementation
10/2025 (Estimated)
Project documents
Rita Morris · rita.morris@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (2), 36 Cfr 220.6(E)(2)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
ForestsHiawatha National Forest
DistrictsRapid River Ranger District; Manistique Ranger District; Munising Ranger District; Sault Ste. Marie Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Rapid River Ranger District · updated 8/27/2025
Behind the Rapid River Ranger District Office near Warehouse H. · Delta, Michigan

Proposed expansion is 50 feet x 90 feet for a total of 0.13 acres to expand parking for wildland fire vehicles and snowplowing.

Facility management
Scoping Start
06/13/2025
Decision
08/2025 (Estimated)
Implementation
09/2025 (Estimated)
Project documents
David Devet · David.Devet@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (21), 36 Cfr 220.6(E)(21)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityFacility Improvements/Construction
ForestsHiawatha National Forest
DistrictsRapid River Ranger District
Legal Land DescriptionNot Applicable
Carp Project Completed
Environmental Assessment · St. Ignace Ranger District · updated 8/21/2025
Proposed activities include vegetation management and a recreation component · Chippewa; Mackinac, Michigan

Vegetation Management and Recreation proposal

Forest products
Scoping Start
01/03/2025
Comment Period
01/04/2025
Objection Period Start
06/13/2025
Decision
08/2025 (Estimated)
Implementation
09/2025 (Estimated)
Project documents
Shane Flickinger · shane.flickinger@usda.gov
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityForest Vegetation Improvements; Dispersed Recreation Mgmt.; Species Habitat Improvements; Road Maintenance; Road Improvements/Construction
ForestsHiawatha National Forest
DistrictsSault Ste. Marie Ranger District; St. Ignace Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Hiawatha National Forest All Units · updated 8/21/2025
four separate project areas: Forest Rd 2231 (Sturgeon River to Rapid River) and adjacent; Brevoort Lake Communities; Pontchartrain Shores and adjacent communities; Forest Rd 3136, Teets Rd and adjacen · Chippewa; Delta; Mackinac, Michigan

The proposed action is needed to provide high speed, broadband internet to communities in Delta, Chippewa, and Mackinac counties through the Mobile Now Act. Rural communities in these locations are underserved.

Special use management
Scoping Start
06/30/2025
Decision
08/2025 (Estimated)
Implementation
08/2025 (Estimated)
Project documents
Mark Fondriest · mark.fondriest@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (2), 36 Cfr 220.6(E)(2)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
ForestsHiawatha National Forest
DistrictsRapid River Ranger District; Manistique Ranger District; Sault Ste. Marie Ranger District; St. Ignace Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · St. Ignace Ranger District · updated 8/21/2025
Round Island Wilderness Area; Scout Camp and Northeast Sandy Beach Camping Areas · Mackinac, Michigan

Replace the two current wilderness toilet structures with moldering style toilet structures and decommission existing toilet structures.

Recreation management
Scoping Start
03/18/2025
Decision
08/2025 (Estimated)
Implementation
09/2025 (Estimated)
Project documents
Andrew Rogers · Andrew.Rogers@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (22), 36 Cfr 220.6(E)(22)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityDeveloped Site Management; Wilderness Management
ForestsHiawatha National Forest
DistrictsSt. Ignace Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Munising Ranger District · updated 8/18/2025
Grand Island National Recreation Area, Mather Lodge Historic Building and Shoreline, Alger County, Munising, MI, Grand Island Township. · Alger, Michigan

The Forest Service is proposing to build alternative power infrastructure (i.e. solar) that would be used to power the infrastructure at Williams Landing and the Grand Island Maintenance Garage.

Recreation managementFacility management
Scoping Start
07/2025 (Estimated)
Decision
08/2025 (Estimated)
Implementation
08/2026 (Estimated)
Project documents
Brian Hinch · brian.hinch@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (21), 36 Cfr 220.6(E)(21)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityFacility Improvements/Construction
ForestsHiawatha National Forest
DistrictsMunising Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Munising Ranger District · updated 8/11/2025
Grand Island National Recreation Area, west shore · Alger, Michigan

This project includes bank stabilization along 200 feet of Lake Superior shoreline in front of the historic Mather-Klauer Lodge on Grand Island National Recreation Area.

Recreation managementHeritage resource managementSpecial area managementFacility management
Scoping Start
09/04/2024
Decision
08/2025 (Estimated)
Implementation
08/2025 (Estimated)
Project documents
Brian Hinch · brianhinch@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.12 (5), 36 Cfr 220.6(D)(5)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityDeveloped Site Management; Facility Improvements/Construction; Heritage Resource Management; Facility Maintenance; Special Area Management; Watershed Improvements
ForestsHiawatha National Forest
DistrictsMunising Ranger District
Legal Land DescriptionGrand Island National Recreation Area - T 48 N, R 19 W, Sec 4
Decision Memo · Sault Ste. Marie Ranger District · updated 8/11/2025
M-123 @ Wilwin Rd. (FR 3145) · Chippewa, Michigan

The Chippewa County SORVA, in cooperation with the Michigan DNR will sign, grade, and potentially harden the approximately 250 foot user-developed trail that runs from M-123 to FR 3421.

Recreation management
Scoping Start
05/29/2025
Decision
07/2025 (Estimated)
Implementation
08/2025 (Estimated)
Project documents
Justin Bomers · justin.bomers@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (1), 36 Cfr 220.6(E)(1)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityTrail Management
ForestsHiawatha National Forest
DistrictsSault Ste. Marie Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Munising Ranger District · updated 6/30/2025
0.1 acres in Delta County - North side of Co Rd 440, 1.18 miles West of Forest Hwy 13 · Delta, Michigan

Installation of underground electric beginning at an existing underground pedestal on the North side of Co Rd 440. From the pedestal via vibratory plow to 2 residents along an existing road right of way.

Special use management
Scoping Start
04/30/2025
Decision
06/2025 (Estimated)
Implementation
06/2025 (Estimated)
Project documents
Evanna Phelps · evanna.phelps@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
ForestsHiawatha National Forest
DistrictsMunising Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Munising Ranger District · updated 6/30/2025
Au Train, Bass, Bear, Boot, Chicago, Clear, Colwell, Corner, East, Fish, Grassy, Ironjaw, Jackpine, Leg, Lion, Lyman, McKeever, Minerva, Mowe, Lake Nineteen, Petes, Red Jack, Sand, Scout, Skeels, Stue · Alger; Delta; Schoolcraft, Michigan

This guide provides guided kayak fishing, canoe floats, kayak tours, fly fishing, fishing classes and ice fishing (Ice fishing will be assessed after the summer season through a new permit if the Forest Service wishes to continue to permit this guide

Recreation managementSpecial use management
Scoping Start
05/01/2025
Decision
06/2025 (Estimated)
Implementation
06/2025 (Estimated)
Brenda Rebitzke · brenda.rebitzke@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.12 (8), 36 Cfr 220.6(D)(8)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
ForestsHiawatha National Forest
DistrictsRapid River Ranger District; Manistique Ranger District; Munising Ranger District
Legal Land DescriptionNot Applicable
Crusher Bike Event Completed
Decision Memo · Munising Ranger District · updated 6/30/2025
Valley Spur and Bruno's Run Trail systems · Alger, Michigan

This is an adventure bike race that covers 500 hundred miles in 5 days from Peninsula Point to Copper Harbor. Will use existing roads and mountain bike trails in Bruno's Run and Valley Spur. Up to 75 racers.

Recreation managementSpecial use management
Scoping Start
05/21/2025
Decision
06/2025 (Estimated)
Implementation
06/2025 (Estimated)
Brenda Rebitzke · brenda.rebitzke@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.12 (8), 36 Cfr 220.6(D)(8)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
ForestsHiawatha National Forest
DistrictsMunising Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Munising Ranger District · updated 6/30/2025
South of Co Rd 440 in the vicinity of the Big Springs North Trailhead · Schoolcraft, Michigan

Temporary use permit for outfitting/guiding services during the 2025 bear season. Will not include the use of bait stations.

Recreation managementSpecial use management
Scoping Start
04/28/2025
Decision
06/2025 (Estimated)
Implementation
09/2025 (Estimated)
Project documents
Brenda Rebitzke · brenda.rebitzke@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.12 (8), 36 Cfr 220.6(D)(8)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
ForestsHiawatha National Forest
DistrictsMunising Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Munising Ranger District · updated 6/30/2025
Several stream crossings along the Haywire Grade Snowmobile/ATV Trail · Schoolcraft, Michigan

Replace one trail/road bridge over the North Branch of the Stutts Creek on the Haywire Grade Snowmobile/ATV Trail. Replace the bridge decking on 10 additional bridges along the trail.

Recreation managementRoad management
Scoping Start
08/01/2024
Decision
06/2025 (Estimated)
Implementation
08/2025 (Estimated)
Project documents
Brenda Rebitzke · brenda.rebitzke@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (23), 36 Cfr 220.6(E)(23)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityTrail Management; Road Maintenance; Road Improvements/Construction; Travel Management
ForestsHiawatha National Forest
DistrictsMunising Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · St. Ignace Ranger District · updated 6/30/2025
St Ignace Ranger District · Mackinac, Michigan

Establish a new population of Lakeside Daisy on the St. Ignace Ranger District. Creation of 1m x 4m plots where planting will occur at 3-5 inches deep.

Wildlife, fish, rare plants
Scoping Start
03/14/2025
Decision
06/2025 (Estimated)
Implementation
06/2025 (Estimated)
Project documents
Julia Hall · julia.hall@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (25), 36 Cfr 220.6(E)(25)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecies Habitat Improvements; Species Population Enhancements
ForestsHiawatha National Forest
DistrictsSt. Ignace Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Sault Ste. Marie Ranger District · updated 6/4/2025
create a create a circuit tie between Trout Lake and Eckerman substations. Installation will consist of approximately three miles of 3%u0278 #350MCM concentric line in a 6" HDPE conduit. · Chippewa, Michigan

This project proposes adding a new line to the existing master special use permit, that will connect two critical substations allowing broader backup coverage of powered service when emergencies or line outages arise across currently isolated circuit

Special use management
Scoping Start
05/05/2025
Decision
05/2025 (Estimated)
Implementation
05/2025 (Estimated)
Project documents
Rita Morris · rita.morris@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityElectric Transmission; Facility Improvements/Construction; Special Use Authorizations
ForestsHiawatha National Forest
DistrictsSault Ste. Marie Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · St. Ignace Ranger District · updated 5/30/2025
Along Highway 123, Interstate 75 and smaller roads in the southern portion of the St. Ignace Ranger District · Chippewa; Mackinac, Michigan

Install, maintain, and operate approximately 31.16 miles/2.35 acres of fiber optic cable, electronics, hand holds and small pedestals to increase broadband connections across the district. 12.12 miles bored, 19.05 miles plowed.

Special use management
Scoping Start
03/25/2025
Decision
05/2025 (Estimated)
Implementation
06/2025 (Estimated)
Project documents
Evanna Phelps · evanna.phelps@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (2), 36 Cfr 220.6(E)(2)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityFacility Improvements/Construction; Special Use Authorizations
ForestsHiawatha National Forest
DistrictsSt. Ignace Ranger District
Legal Land DescriptionNot Applicable