Needs exist in the project area include wildlife habitat improvement. Possible treatments include vegetation management and prescribed fire.
Location
Boundary includes all of the Sitlington Creek-Greenbrier River watershed within the forest proclamation boundary. It centers around Marlinton, WV
Project timeline
1
Scoping Start
08/2026 (Estimated)
2
Comment Period
08/2026 (Estimated)
3
Objection Period Start
12/2026 (Estimated)
4
Decision
02/2027 (Estimated)
5
Implementation
05/2027 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Species Habitat Improvements; Roadless Area Management; Road Maintenance; Road Improvements/Construction; Timber Sales (Green) |
| Forests | Monongahela National Forest |
| Districts | Marlinton Ranger District |
| Legal Land Description | Not Applicable |