Upper dam is located on the East Branch Ontonagon River. Upper dam consists of old timber, metal pipes, as well as tree material placed by beavers. This project proposes to remove the dam to restore the area to natural conditions and allow for
Location
Kenton Ranger District
Project timeline
1
Scoping Start
12/01/2023
2
Decision
02/2025 (Estimated)
3
Implementation
05/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (18), 36 Cfr 220.6(E)(18) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Watershed Improvements |
| Forests | Ottawa National Forest |
| Districts | Kenton Ranger District |
| Legal Land Description | Not Applicable |