about 641 feet of aerial line will run starting from an existing pole to 2 new poles and then to the doser. brush removal will be needed, and brush will be chipped. Traffic plans will comply with state and county safety guidelines.
Location
the powerline installation will start on the west side of SR 78 and will finish on the east side of SR 78 running alongside the road or spanning across it. WNF, Athens District, Hocking County Ohio
Project timeline
1
Scoping Start
05/09/2025
2
Decision
06/2025 (Estimated)
3
Implementation
06/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Ohio Power Snow Fork Doser SUP | Decision Signed Date: 06/16/2025 |
| Forests | Wayne National Forest |
| Districts | Athens Ranger District |
| Legal Land Description | Section 2, Township 13N, Range 15W |