Decision Memo Completed

Chugach Electric Association Portage to Whittier Shore Power Line Rebuild

Chugach National Forest Anchorage, Alaska Chugach National Forest All Units

CEA has proposed a line rebuild between Portage and Whittier to provide shore power to the Whittier cruise ship terminals.

Location

Portage valley; between the electric substation located east of the Seward Highway/Portage Glacier Highway intersection to Section 14, T8N, R3E west of the Whittier Tunnel

Project timeline

1
Scoping Start
04/14/2025
2
Decision
12/2025 (Estimated)
3
Implementation
06/2026 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (2), 36 Cfr 220.6(E)(2)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Chugach Electric Association Portage to Whittier Shore Power Line RebuildDecision Signed Date: 12/23/2025
ForestsChugach National Forest
DistrictsGlacier Ranger District
Legal Land DescriptionNot Applicable