The BDNF is considering issuing a special use permit for the construction and operation of an Interoperability Montana (IM) communication site on Ellis Peak.
Location
Ellis Peak in the Tendoy Mountains about 36 miles southwest of Dillon, MT
Project timeline
1
Scoping Start
07/21/2008
2
Comment Period
12/22/2008
3
Decision
04/2009 (Estimated)
4
Implementation
06/2009 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Interoperable Montana Communications Project Southwest Loop | Decision Signed Date: 04/21/2009 Legal Notice Date: 04/22/2009 |
| Forests | Beaverhead-Deerlodge National Forest |
| Districts | Dillon Ranger District |
| Legal Land Description | T12S, R12W, Sec. 36 |