This project iwould move the Dry Hollow storage tank point of diversion in the Electric Fence pasture about 1740 feet, add a trough, and reconstruct 1.11 mi. of existing pipeline to protect a resource at the original point of diversion.
Location
Pioneer Landscape, East Face Management Area
Project timeline
1
Scoping Start
05/23/2016
2
Decision
08/2016 (Estimated)
3
Implementation
10/2016 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Grazing Structural Improvements |
| Vipond Water Development | Decision Signed Date: 08/30/2016 |
| Forests | Beaverhead-Deerlodge National Forest |
| Districts | Wise River Ranger District |
| Legal Land Description | T2S, R10W, Sections 12, 13, 14 & 18 |