Decision Memo Completed

Vipond Water Development

Beaverhead-Deerlodge National Forest Beaverhead, Montana Beaverhead-Deerlodge National Forest All Units

This project iwould move the Dry Hollow storage tank point of diversion in the Electric Fence pasture about 1740 feet, add a trough, and reconstruct 1.11 mi. of existing pipeline to protect a resource at the original point of diversion.

Location

Pioneer Landscape, East Face Management Area

Project timeline

1
Scoping Start
05/23/2016
2
Decision
08/2016 (Estimated)
3
Implementation
10/2016 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityGrazing Structural Improvements
Vipond Water DevelopmentDecision Signed Date: 08/30/2016
ForestsBeaverhead-Deerlodge National Forest
DistrictsWise River Ranger District
Legal Land DescriptionT2S, R10W, Sections 12, 13, 14 & 18
Grazing management